Infrastructure tracker

Louisiana data centers: map, projects, and status

Start here: the tracked buildout in one paragraph.

LouisianAI tracks 4 source-backed AI records: 3 named campuses and 1 multi-campus program. 3 watch records stay separate. The core register has a $71.6B+ disclosed-capex floor; published site MW is counted only where a source discloses a number. Generation and grid-enabling projects remain in the LPSC docket trail, not the campus totals. Hut 8's up-to-$10B Phase I ceiling stays visible on its record but outside the statewide floor.

4 core records + 3 watch rows · $71.6B+ disclosed-capex floor · 5,760 MW published site power · edition 2026.11.25
Core capex
$71.6B+
Published site MW
5,760
Active builds
3 / 4
LPSC dockets
4 open / 6
Operators
4
Parishes
5
Primary source

Project Intelligence

The Louisiana AI infrastructure tracker for source-linked project status, parish, operator, power demand, timeline, and verification signals.

Decision lens

Evidence coverage in the current view

Filter by research posture without changing the published record. Linked source rows measure catalog coverage; project pages remain the record-level source trail.

Visible records
7
Verified
0
Records with sources
6/7
Linked source rows
18

7 records in the active research lens

OperatorParishStatusKey intelligenceInvestigation
Amazon Data Centers in Caddo & BossierAmazon / STACKCaddo & BossierAnnounced$18B3 linked · ReportedTrack how the linked Caddo, Blanchard, Bossier, and Resilient Technology Park sites separate into their own permitting records. Water-service agreements, cooling-water discharge, wetlands buffers, substations, the pendin…
Cameron Campus Data Center No. 2 applicationCameron Generation, LLCCameronApplication filed—7 linked · Reported
Delta Forge 1Applied DigitalRapidesUnder construction$3.6B3 linked · ReportedWatch Cleco delivery work, any project-specific LPSC proceedings, and the unresolved site-size scopes: Applied Digital has described more than 500 and more than 600 acres, while Louisiana's rollout describes approximatel…
Hut 8 River Bend Data CenterHut 8West FelicianaUnder construction$10B2 linked · ReportedKey watch items are Entergy service milestones, Hut 8's $16M parish water-system expansion, closed-loop cooling claims, and how much of the 1 GW potential becomes commercialized beyond the 245 MW initial lease.
Meta Hyperion AI Data CenterMeta PlatformsRichlandUnder construction$50B2 linked · ReportedWatch U-37425 and U-37882, Entergy substation and transmission work, groundwater reporting, and the ratepayer-cost debate around the larger Hyperion buildout. Labor, civil, and support-service demand remains one of north…
STACK Bossier site contextSTACK InfrastructureBossierWatch—1 linked · Seed
Vantage East BankVantage Data CentersEast Baton RougeRumoured—0 linked · Seed

Verification posture

The evidence lens is a view over the current catalog. Confidence class and linked-source count make research posture explicit, while the full CSV/JSON exports preserve the complete machine-readable set.

Sources: LED filings • parish permits and dockets • utility interconnection filings • official operator updates. Pair this view withProject Intelligence cards,methodology briefs, andthe vendor ecosystem.

VERIFIED PRIMARY SOURCES • INDEPENDENT • RELEASE CYCLE STAMP
Statewide inventory

How many data centers are in Louisiana?

Directories count 23 (DataCenterMap) to 29 (dcmap.us, 19 operational) data center sites in Louisiana as of October 2026. LouisianAI tracks 4 source-backed AI records — named campuses and multi-campus programs: Meta Hyperion AI Data Center, Amazon Data Centers in Caddo & Bossier, Hut 8 River Bend Data Center, and Delta Forge 1. Retrieved October 12, 2026. Directory totals are not added together or to the sourced AI register because inclusion rules differ and overlap is unverified.

Across all 4 core records, the register identifies 3 under construction and 1 announced. It reports 5,760 MW of published site power across 3 records. This reflects the disclosed compute-capacity, utility-capacity, or utility-design basis, not an in-service load total.

Register as of 2026-11-18. See counting rules or download the dataset.

Source-backed AI records
4
3 campuses and 1 multi-campus program
Disclosed capex floor
$71.6B+
Separate from upper-bound disclosures
Published site power
5,760 MW
3 records disclose MW
Disclosed floorspace
4.0M+ sq ft
Meta disclosure, not a statewide total

Source-backed projects by parish

A multi-parish program is shown once so its investment and power are not counted twice.

ParishRecordsInvestmentPower
Richland1$50.0B+5,000 MW
Caddo & Bossier1$18.0BNot disclosed
Rapides1$3.6B430 MW
West Feliciana1No disclosed floorUp to $10.0B330 MW

Cited facility inventories

Directory totals use different inclusion rules, and overlap is unverified. Directory totals are not added together or added to this register.

  • LouisianAI sourced AI register: 4

    0 operating, 3 under construction, 1 announced.

  • DataCenterMap: 23

    23 facilities across 5 markets (Baton Rouge 5, New Orleans 6, Shreveport 10, Alexandria 1, Monroe 1)

    DataCenterMap does not publish an operating / planned split on its Louisiana state page. The 23-facility total is a directory listing, not a LouisianAI-verified campus register.

  • dcmap.us: 29

    29 sites: 19 operational, 4 under construction, 5 planned, 1 paused

    dcmap.us mixes colocation, hyperscale, research/HPC, and pipeline records and counts named phases separately. Its 19 operational figure is the directory's claim, not a LouisianAI-sourced operating count.

Directory counts retrieved October 12, 2026.

What the project records tell us

Louisiana AI infrastructure tracker

The Louisiana AI infrastructure tracker separates source-backed named campuses, source-backed multi-campus programs, and visible watch-list rows. Its statewide denominator counts a campus once or an announced multi-campus program once; it does not infer undisclosed MW, double-count a subsite, or add enabling generation to data-center totals.

Louisiana data center timeline

The Louisiana data center timeline starts with source-backed hyperscale AI records after 2024: Meta Hyperion is under construction in Richland Parish, Amazon/STACK is preparing Caddo and Bossier campuses, Hut 8 River Bend is under construction, and Applied Digital Delta Forge 1 is under construction in Rapides Parish. Delta Forge 1 targets initial operations in mid-2027; every forward date still depends on utility, regulatory, and construction milestones.

Louisiana data center power demand

Louisiana's core data-center register has 5.76 GW of published site power across three records: Meta's 5 GW compute-capacity build-out, Hut 8's 330 MW utility capacity, and Delta Forge 1's 430 MW total utility design. Amazon/STACK's $18B program has no public MW figure, so it is not estimated. Enabling generation and grid work belong in the LPSC docket trail, not this campus total.

Largest AI investment Louisiana

For a single Louisiana AI data center campus, Meta Hyperion in Richland Parish is the largest tracked investment — more than $50 billion after the July 13, 2026 expansion announcement — and the largest planned power load at a confirmed 5 GW. For a named multi-site cloud/data-center program, Amazon/STACK's Caddo and Bossier campuses are the largest disclosed package at $18B. LouisianAI separates single-campus scale from multi-site program scale so the ranking is auditable.

Meta Hyperion aliases

Meta Hyperion data center Louisiana, Meta Hyperion Richland Parish, Hyperion data center, Project Sucre, Meta Richland Parish Data Center, Meta Hyperion 5GW Louisiana, and Richland Parish Data Center all point to the same source-tracked Meta campus in Richland Parish. The canonical LouisianAI profile is /data-centers/meta-hyperion, with LPSC, power, water, Wikidata, and Wikipedia links attached there.

Louisiana data center operators

The source-backed AI-buildout operator map is Meta in Richland Parish, Amazon Web Services with STACK in Caddo and Bossier Parishes, Hut 8 at River Bend in West Feliciana Parish, and Applied Digital at Delta Forge 1 in Rapides Parish. Amazon AWS Caddo Parish data center and Amazon AWS Bossier Parish data center route to the one Amazon/STACK program until individual public site records separate them; Hut 8 River Bend Louisiana data center routes to West Feliciana Parish; Applied Digital Project Lightning Louisiana remains the legacy query path to the official Delta Forge 1 profile.

Water and environmental controls

Louisiana data center water usage is not a statewide average; it is a project-by-project permit question. Meta Hyperion is the main public water-use record today, Amazon pairs its Caddo and Bossier build with regional water infrastructure commitments, and river-adjacent campuses such as Hut 8 River Bend depend on cooling, withdrawal, discharge, parish, Louisiana Department of Conservation and Energy groundwater, and LDEQ water-permit records.

By metro area

Open a metro overview for local projects, parishes, and the evidence behind the buildout.

Sources and open data

The infrastructure dataset uses project-level records from Louisiana Economic Development, the Louisiana Public Service Commission, SEC filings, parish permits, and operators. The raw dataset is available under CC BY 4.0.

Questions about the tracker

Frequently asked questions

What is the Louisiana AI infrastructure tracker?

The Louisiana AI infrastructure tracker is the source-linked LouisianAI dataset at /data-centers. It tracks AI data-center records by operator, parish, investment, power demand, status, timeline, and primary-source support.

Why does this count differ from other data center trackers?

Trackers count different things. Colocation directories list operating facilities by address, and building-level trackers count each building on a campus separately. This register counts a campus or a multi-campus program once, and only when a named public source documents it. Unconfirmed sites stay visible as watch rows and are left out of every total. Generation and transmission projects are tracked in the LPSC docket trail and are not added to campus power.

What is the Louisiana data center timeline?

The Louisiana data center timeline starts with Meta Hyperion under construction in Richland Parish, Amazon and STACK's multi-campus northwest Louisiana buildout after the March 2026 Bossier final plat, Hut 8 River Bend's 245 MW Phase I lease plus parish water-system work, and Applied Digital Delta Forge 1 after its January 2026 groundbreaking and mid-2027 operations target.

What is Louisiana data center power demand?

Louisiana data center source records disclose 5.76 GW of site power across 3 records. Amazon/STACK's $18.0B multi-campus program has no public MW figure, so it is not guessed; generation, transmission, storage, and renewable projects are tracked separately in the LPSC docket trail rather than added to campus power.

What is Louisiana data center capex announced?

Louisiana's core tracker denominator has a $71.6B+ source-backed disclosed-capex floor: $53.6B+ in named campus records and $18.0B in the Amazon/STACK multi-campus program, counted once. Hut 8's up-to-$10.0B Phase I ceiling is visible separately and not added to that floor. Watch rows and grid-enabling projects are intentionally excluded.

What data infrastructure exists in New Orleans, LA?

New Orleans operational-colocation coverage is separate from this source-backed AI-buildout denominator. DataCenterMap lists 23 facilities statewide as of October 12, 2026, including New Orleans-market listings; LouisianAI does not add those directory rows to the sourced AI headline until each has its own project-level source trail. The current verified AI records are in Richland, Caddo and Bossier, West Feliciana, and Rapides parishes.

What is Meta Hyperion data center status in 2026?

Meta Hyperion is under construction in Richland Parish in 2026. It is the largest tracked Louisiana AI data center, with a confirmed 5 GW build-out costing more than $50 billion, announced by Meta on July 13, 2026.

Which operators are building Louisiana AI data centers?

The Louisiana operator set is Meta in Richland Parish, Amazon Web Services with STACK in Caddo and Bossier Parishes, Hut 8 at River Bend in West Feliciana Parish, Applied Digital at Delta Forge 1 in Rapides Parish, plus operational colocation operators in Baton Rouge and New Orleans.

What is Louisiana data center water and environmental impact?

Louisiana data center water and environmental impact is project-specific: cooling design, permitted withdrawals, discharge path, parish water agreements, and LDEQ/LPSC records. Meta Hyperion has the most visible water-use record; Amazon has regional water-infrastructure commitments; Hut 8 and Applied Digital require site-level permit tracking.

Where do Louisiana secondary watch items and local policy actions live?

LouisianAI keeps unconfirmed site-control cases and parish or city policy moves off the canonical tracker until operator, permit, or utility records harden. The current dated holding surface covers Resilient Technology Park, State Line / Blanchard, the New Orleans data-center interim zoning district, and St. Charles Parish's data-center zoning code.

How many data centers are in Louisiana?

Directories count 23 (DataCenterMap) to 29 (dcmap.us, 19 operational) data center sites in Louisiana as of October 2026. LouisianAI tracks 4 source-backed AI records — named campuses and multi-campus programs: Meta Hyperion AI Data Center, Amazon Data Centers in Caddo & Bossier, Hut 8 River Bend Data Center, and Delta Forge 1. Retrieved October 12, 2026. Directory totals are not added together or to the sourced AI register because inclusion rules differ and overlap is unverified.

Where is the Louisiana data center map and list?

The statewide data-center tracker at /data-centers has the interactive map, sortable project list, parish filters, and dated statewide count. These views use the same source-backed infrastructure register.

How many AI data centers are being built in Louisiana?

LouisianAI's source-backed statewide register has 4 current AI data-center records as of November 18, 2026: 3 named campuses under construction (Meta Hyperion, Hut 8 River Bend, and Applied Digital Delta Forge 1) plus Amazon/STACK's announced multi-campus Caddo/Bossier program.

What is Meta Hyperion data center status in Louisiana in 2026?

Meta Hyperion is under construction in Richland Parish as of July 2026. It is the largest tracked Louisiana AI data center: on July 13, 2026 Meta confirmed a 5 GW build-out costing more than $50 billion, with roughly 2 GW expected by 2030 and the full campus around 2032, on about 2,250 acres with roughly 4 million square feet.

What is the largest data center in Louisiana?

Meta's Hyperion AI data center in Richland Parish is the largest by every metric: more than $50 billion of committed capital, a confirmed 5 gigawatt (5,000 MW) compute build-out, and ~4 million square feet of campus floorspace. It is also Meta's largest data center anywhere in the world and is currently under construction.

Which Louisiana parishes have the most data centers?

The core source-backed register covers Richland (Meta), Caddo and Bossier (Amazon/STACK's single multi-campus program), West Feliciana (Hut 8), and Rapides (Applied Digital). Richland accounts for at least $50 billion of the $71.6B+ disclosed-capex floor because Meta's current disclosure is a $50B-plus lower bound. Hut 8's up-to-$10 billion Phase I ceiling remains separately marked rather than added to that floor.

How much new electricity will Louisiana data centers need?

The core register has 5,760 MW of published site power across Meta, Hut 8, and Applied Digital, measured on each operator's disclosed basis rather than normalized into a utility forecast. Amazon/STACK's MW is not public. Entergy generation, transmission, storage, and renewable proposals are enabling infrastructure with their own LPSC review and are not added to the data-center MW denominator.

What incentives are Louisiana data centers receiving?

Act 730 provides a sales-and-use-tax exemption for qualifying data-center purchases. Eligibility for ITEP and any parish PILOT agreement requires a separate project-specific record. Louisiana Quality Jobs closed to new advance notifications after June 30, 2025. The incentives register links the governing instruments and distinguishes eligibility from a campus award.

When will these Louisiana data centers be operational?

Meta Hyperion is targeting initial operations in late 2027, with roughly 2 GW expected by 2030 and the full 5 GW build-out around 2032 per Meta's July 2026 announcement. Amazon/STACK's first Northwest Louisiana campus is targeting 2027–2028. Hut 8 River Bend Phase 1 is targeting 2027. Applied Digital expects initial Delta Forge 1 operations in mid-2027. Each project's specific milestone schedule is tracked on its detail page.

Which operators are building Louisiana data centers?

The current source-backed AI-buildout operators are Meta in Richland Parish, Amazon Web Services with STACK Infrastructure in Caddo and Bossier Parishes, Hut 8 in West Feliciana Parish, and Applied Digital in Rapides Parish. LouisianAI keeps the Amazon/STACK announcement as one multi-campus program until public records separate individual sites.

What is the water and environmental issue for Louisiana data centers?

The water and environmental issue is project-specific: cooling design, permitted withdrawals, discharge path, local water supply agreement, parish approvals, Louisiana Department of Conservation and Energy groundwater controls, and LDEQ water permits. Meta Hyperion has the most visible water-use record; Amazon has public regional water-infrastructure commitments; Hut 8 and Applied Digital require site-level verification as permits and cooling disclosures harden.