§ Tracker / Rapides Parish / Applied Digital
Share on XShare on LinkedIn
Under constructionDelta Forge 1Conf · CCurrent
Tracker / Rapides Parish / Applied Digital

Delta Forge 1.

Louisiana Economic Development announced Delta Forge 1 as a $3.6 billion Rapides Parish AI factory build. Applied Digital describes 430 MW of total utility power, up to 300 MW of critical IT load, and initial operations targeted for mid-2027. Local reporting documented Project Lightning as an internal development codename; it is an alias, not an operator-confirmed project name.

What matters first for Delta Forge 1

Applied Digital's Delta Forge 1 campus is under construction near Boyce. Public company and Louisiana Economic Development materials describe 430 MW of total utility power, up to 300 MW of critical IT load, more than 200 full-time jobs, and more than 1,000 peak construction jobs, with initial operations targeted for mid-2027. Follow this profile for the current status, utility posture, water or permit controls, source links, and alias terms that engines and readers use for the same campus.

672 acres · Not disclosed · last sync
Operator
Applied Digital
Parish
Rapides Parish
Utility
Cleco
Peak MW
430 MW
Capex
$3.6B
Sq ft
Verification needed
Acres
672 acres
Confidence
C
Entity bridge

Delta Forge 1 is Applied Digital's official name for the Rapides Parish campus. Local reporting documented Project Lightning as an internal development codename, so Project Lightning searches resolve to this profile.

What is Delta Forge 1 in Louisiana? Applied Digital's Delta Forge 1 campus is under construction near Boyce. Public company and Louisiana Economic Development materials describe 430 MW of total utility power, up to 300 MW of critical IT load, more than 200 full-time jobs, and more than 1,000 peak construction jobs, with initial operations targeted for mid-2027. The canonical local profile is this page: /data-centers/delta-forge-1.

The important search bridge is naming: Delta Forge 1 is the company-announced name, while local reporting documented Project Lightning as an internal development codename that still appears in searches. The power answer must keep 430 MW of total utility design separate from up to 300 MW of critical IT load and distinguish the 672-acre acquired parcel record from Applied Digital's more-than-500 and more-than-600-acre campus descriptions and Louisiana's approximately 300-acre initial-facilities scope.

Alias cluster · canonicalized here
Applied Digital Project Lightning
Applied Digital Delta Forge 1
Delta Forge 1
Applied Digital Boyce data center
Applied Digital Rapides Parish AI factory
Applied Digital Louisiana AI factory
Project Lightning AI factory campus
Same tracked project cluster: Delta Forge 1, Applied Digital Delta Forge 1, Applied Digital Boyce data center, Applied Digital Rapides Parish AI factory, and Applied Digital Louisiana AI factory point to the Applied Digital campus near Boyce. Project Lightning is a locally documented internal codename, not an operator-confirmed project name.

What is Delta Forge 1 in Louisiana?

Delta Forge 1 is Applied Digital's company-announced name for the Louisiana AI factory campus near Boyce in Rapides Parish. Local reporting documented Project Lightning as an internal development codename for the same campus.

What is Applied Digital Project Lightning Louisiana?

Applied Digital Project Lightning Louisiana is a legacy search phrase for the Rapides Parish project tracked here as Delta Forge 1. Applied Digital's official project name is Delta Forge 1; local reporting documented Project Lightning as an internal development codename, but reviewed operator primary sources do not establish it as an official project name.

How much power will Delta Forge 1 use?

Applied Digital says Delta Forge 1 is designed for 430 MW of total utility power across two facilities, enabling up to 300 MW of critical IT load. Cleco is the confirmed serving utility; no project-specific LPSC docket or approval was identified in the reviewed record.

Where is Applied Digital's Louisiana AI factory?

Applied Digital's Louisiana AI factory is in Rapides Parish near Boyce. LouisianAI routes Boyce data center, Delta Forge 1, Applied Digital Rapides Parish AI factory, and Project Lightning searches to this canonical project profile and the Rapides Parish hub.

When is Applied Digital targeting operations in Louisiana?

Applied Digital and Louisiana Economic Development both say initial Delta Forge 1 operations are targeted for mid-2027, subject to construction execution, utility delivery, and final site buildout.

Desk thesis

The campus IS the load.

Louisiana Economic Development announced Delta Forge 1 as a $3.6 billion Rapides Parish AI factory build. Applied Digital describes 430 MW of total utility power, up to 300 MW of critical IT load, and initial operations targeted for mid-2027. Local reporting documented Project Lightning as an internal development codename; it is an alias, not an operator-confirmed project name.

Source-linked claim table
ClaimValueSource
Capex range$3.6B [1][2][3][4][5][6][7][8][9][10][11][12]Louisiana Economic Development
Power capacity430 MW [1][2][3][4][5][6][7][8][9][10][11][12]Louisiana Economic Development
Site size672 acres · Verification needed [1][2][3][4][5][6][7][8][9][10][11][12]Louisiana Economic Development
Jobs200 permanent · 1,000 construction [1][2][3][4][5][6][7][8][9][10][11][12]Louisiana Economic Development
Louisiana incentive postureAct 730 sales/use tax exemption and local PILOT structures require document-level verification. [13]Louisiana Legislature
Sales/use tax and PILOT frameworkLouisiana Act 730 and local PILOT structures are tracked as separate legal/economic artifacts. [13]Louisiana Legislature
Entity aliasesDelta Forge 1, Applied Digital Delta Forge 1, Applied Digital Boyce data center, Applied Digital Rapides Parish AI factory, and Applied Digital Louisiana AI factory point to the Applied Digital campus near Boyce. Project Lightning is a locally documented internal codename, not an operator-confirmed project name. [1][2][3][4][5][6][7][8][9][10][11][12]Louisiana Economic Development
Timeline

Public record.

  1. Jan 22, 2026
    Project publicly announced or entered the source-backed watch queue.
  2. Jan 22, 2026
    Groundbreaking or civil mobilization milestone recorded.
  3. Jan 22, 2026
    Applied Digital announced that Delta Forge 1 had broken ground.
  4. May 26, 2026
    Louisiana Economic Development publicly identified Delta Forge 1 in Rapides Parish and Cleco confirmed it would provide power.
Economic impact calculator

Stress-test the assumptions.

Edit the inputs to compare an ad-valorem proxy against a PILOT discount, construction labor hours, and peak power demand relative to an editable parish consumption baseline.

Ad-valorem proxy

$396,000,000

PILOT proxy

$217,800,000

Construction job hours

4,160,000

Demand vs parish use

3.1x

What to watch next

The next filings, in plain sight.

  • LPSC docket activity for generation, transmission, and rate-base recovery tied to data-center load.
  • Rapides Parish permit, council, police jury, and economic-development agendas.
  • Operator press rooms, SEC filings, and investor presentations for delivery dates, lease economics, and tenant commitments.
  • Utility substation, transformer, and transmission-procurement signals near the site.
  • Workforce board, contractor, and supplier notices that usually precede peak construction demand.
Power and ratepayer questions roll up through the LPSC data center docket tracker, which normalizes the active filings and source links.
FAQ

Recurring questions, answered.

What is Delta Forge 1 in Louisiana?

Delta Forge 1 is Applied Digital's company-announced name for the Louisiana AI factory campus near Boyce in Rapides Parish. Local reporting documented Project Lightning as an internal development codename for the same campus.

What is Applied Digital Project Lightning Louisiana?

Applied Digital Project Lightning Louisiana is a legacy search phrase for the Rapides Parish project tracked here as Delta Forge 1. Applied Digital's official project name is Delta Forge 1; local reporting documented Project Lightning as an internal development codename, but reviewed operator primary sources do not establish it as an official project name.

How much power will Delta Forge 1 use?

Applied Digital says Delta Forge 1 is designed for 430 MW of total utility power across two facilities, enabling up to 300 MW of critical IT load. Cleco is the confirmed serving utility; no project-specific LPSC docket or approval was identified in the reviewed record.

Where is Applied Digital's Louisiana AI factory?

Applied Digital's Louisiana AI factory is in Rapides Parish near Boyce. LouisianAI routes Boyce data center, Delta Forge 1, Applied Digital Rapides Parish AI factory, and Project Lightning searches to this canonical project profile and the Rapides Parish hub.

When is Applied Digital targeting operations in Louisiana?

Applied Digital and Louisiana Economic Development both say initial Delta Forge 1 operations are targeted for mid-2027, subject to construction execution, utility delivery, and final site buildout.

How big is Delta Forge 1?

Delta Forge 1 is tracked at Verification needed and 672 acres, with 430 MW of power capacity where public sources support the number.

How many jobs will Delta Forge 1 create?

Current tracked figures show 200 permanent jobs and 1,000 construction jobs, subject to source verification.

What is the PILOT agreement for Delta Forge 1?

A PILOT is a payment-in-lieu-of-taxes structure negotiated locally; this page tracks the public artifacts needed to compare ad-valorem exposure with negotiated payments.

When will Delta Forge 1 come online?

Under construction. Exact phase delivery dates remain tied to operator updates, utility milestones, parish permits, and regulatory filings.

Which parish is Delta Forge 1 in?

Delta Forge 1 is tracked in Rapides Parish, Louisiana.

Who is the operator of Delta Forge 1?

Applied Digital is the operator listed for Delta Forge 1.

How much water will Delta Forge 1 use?

Water use is tracked as a verification item because definitive cooling and withdrawal figures usually appear in permits, utility exhibits, or operator environmental disclosures.

What incentives did Louisiana give Applied Digital?

Louisiana data-center incentives can include Act 730 sales/use tax treatment and local PILOT structures; the exact package should be verified against state, parish, and operator documents.

What power infrastructure serves Delta Forge 1?

The page tracks substations, transmission watch corridors, and utility filings as source-backed signals rather than engineering-grade interconnection maps.

Why does LouisianAI label confidence levels?

Confidence labels distinguish seed, reported, and verified claims so readers can separate early intelligence from document-backed facts.

Subscribe

Project-specific milestone alerts.

Cite this page or subscribe to filings that mention Delta Forge 1.

By submitting, you ask LouisianAI to use this information for this request as described in the Privacy Notice.

Cited sources · 13 linked

The public record, linked.

[1]
Primary recordLouisiana Economic Development · 2026-05-26
Open →
[3]
LouisianAI methodology

LouisianAI methodology and reuse guardrails; not an independent project fact source.

ReportingLouisianAI
Open →
[4]
England Authority advance on PILOT + Applied Digital project

Local governance artifact covering PILOT advancement.

ReportingRapides Parish Journal · 2026-04-24T00:00:00.000Z
Open →
[5]
Alexandria broadcast reporting on Boyce industrial rezoning

Regional reporting tying parish rezoning actions to Boyce site.

ReportingKALB · 2026-03-02T00:00:00.000Z
Open →
[6]
England Authority negotiation reporting

Early-phase reporting naming Applied Digital pursuit.

ReportingRapides Parish Journal · 2026-01-22T00:00:00.000Z
Open →
[7]
Rapides Parish Clerk of Court (official portal)

Primary parish civil records portal for instrument retrieval.

ReportingRapides Parish Clerk of Court
Open →
[8]
Applied Digital fiscal third quarter 2026 earnings release

SEC-hosted company source confirming Delta Forge 1 construction, 430 MW total utility design, up to 300 MW critical IT load, more-than-600-acre framing, and mid-2027 operations target.

Primary recordApplied Digital / U.S. SEC · 2026-04-08T00:00:00.000Z
Open →
[9]
Cleco to power data center planned for Rapides Parish

Utility source confirming Cleco service, Rapides Parish, more than 1,000 construction jobs, about 200 long-term jobs, and customer-cost safeguards.

Primary recordCleco · 2026-05-26T00:00:00.000Z
Open →
[10]
What early documents confirm about Applied Digital in Rapides Parish

Records-request reporting citing the 672.52-acre EEIDD application, the approximately 300-acre initial two-building scope, and future-use acreage.

ReportingKALB · 2026-06-25T00:00:00.000Z
Open →
[11]
Applied Digital DevCo financing disclosure

Primary securities disclosure for a development facility supporting new data center projects; it does not identify Delta Forge 1, Louisiana acreage, or project capex.

Primary recordApplied Digital / SEC EDGAR · 2025-12-18T00:00:00.000Z
Open →
[12]
Construction reporting at Boyce data center site

Local reporting documenting the Project Lightning internal codename, a 672-acre acquired site, and visible construction activity near Boyce.

ReportingRapides Parish Journal · 2026-03-25T00:00:00.000Z
Open →
[13]
Louisiana Legislature bill and Act search for Act 730 data-center exemptions

Primary state-law lookup surface for Act 730 sales/use tax exemption and local PILOT diligence.

Primary recordLouisiana Legislature
Open →