Skip to main content
LIVEResearch desk operatingU-37425Entergy LA filing · 7.2 GW load additionRICHLANDHyperion phase 3 permit acceptedCADDOSTACK substation civil mobilisingW. FELICIANAHut 8 River Bend hearing 06/03
§ Operators / hyperscalers / applied-digital
A
Operator dossier · hyperscaler

Applied Digital

NASDAQ:APLD·Dallas, TX·Tracked since 19 Jan 2026·Active
1 LA campuses300 MW critical IT announced$3.6B capexLead: Forge
LA footprint
672 ac
Firm load
300 MW critical IT
Capex announced
$3.6B
Construction peak
200+ permanent · 1,000+ construction
First commissioning
Mid-2027
Direct answer

What is Applied Digital's Louisiana data center footprint?

Applied Digital's confirmed Louisiana footprint is Delta Forge 1 near Boyce in Rapides Parish. Primary sources show the campus under construction with 430 MW of total utility design, up to 300 MW of critical IT load, Cleco as the power provider, and initial operations expected in mid-2027. Local reporting documented Project Lightning as an internal development codename; it remains a legacy query and stable tracker slug, not an operator-confirmed project name.

All projectsLPSC docketsPower topicWater topicDelta Forge 1Applied DigitalApplied Digital CorporationApplied Digital Delta Forge 1Delta Forge 1Applied Digital Project Lightning
Louisiana sites

Active campuses, in order of announcement.

Parishes where Applied Digital operates

The parish footprint.