What is the Louisiana data center LPSC docket?
The Louisiana data center LPSC docket trail has four LouisianAI control records: U-37425 for approved Meta Hyperion Phase 1 service, U-37882 for the open Meta expansion / Project Evest filing, U-37853 for Entergy's Waterford 6 and Westlake generation request, and X-37921 for large-load guidelines.
What is Entergy Louisiana data center power?
Entergy Louisiana data center power is governed through the LPSC docket trail. U-37425 approved the first Meta Hyperion package; U-37882 seeks certification for more than 5,200 MW of additional generation plus 500 kV transmission, storage, nuclear uprates, and renewables; U-37853 is the broader Waterford 6 / Westlake generation filing.
What is Entergy Louisiana data center load?
Entergy Louisiana data center load is the large-load demand tied to Meta Hyperion, later Meta expansion filings, and broader Louisiana industrial growth. The control records are U-37425 for Meta Phase 1, U-37882 for the Meta expansion package, U-37853 for Waterford 6 / Westlake generation, and the LPSC large-load guideline repository X-37921.
What is Louisiana data center Entergy interconnection?
Louisiana data center Entergy interconnection means the regulatory and physical path for connecting large AI load to Entergy generation, substations, 500 kV transmission, customer agreements, collateral, and tariffs. For Meta Hyperion, U-37425 and U-37882 are the public controls for what can energize, who pays, and when the load can be served.
What is Hut 8 River Bend Louisiana data center power?
Hut 8 River Bend Louisiana data center power is an Entergy-served West Feliciana Parish question centered on the River Bend project profile, Entergy service, the public 245 MW anchor lease, and project/LPSC evidence for energization. It should not be confused with SWEPCO's Amazon Caddo/Bossier corridor.
What is SWEPCO Louisiana data center?
SWEPCO Louisiana data center searches point to AEP SWEPCO's northwest Louisiana service territory and Amazon's $12 billion Caddo + Bossier Parish campus program. LouisianAI separates that SWEPCO/Amazon corridor from the Entergy Meta and Hut 8 docket trail.
Which utility powers Amazon AWS Caddo and Bossier data centers?
AEP SWEPCO is the utility of record for Amazon AWS Caddo and Bossier data centers. The canonical answer path is the Amazon project profile, the Amazon operator hub, the Caddo and Bossier parish hubs, and the power topic; the LPSC docket page remains the control surface for large-load tariff and ratepayer-protection context.
What is Louisiana data center peak power MW?
Louisiana data center peak power MW is not a single published IT-load number. The source-backed public proxy is the docketed utility build: U-37425 for Meta Phase 1, U-37882 for more than 5,200 MW of expansion generation and transmission, U-37853 for Waterford 6 and Westlake, plus project-level MW rows on LouisianAI.
What are Louisiana data center permits?
Louisiana data center permits combine parish zoning or site approval, LDEQ air and water permits where applicable, LPSC utility filings for power and tariffs, and federal reviews only when triggered. The LPSC page is the control surface for power permits and ratepayer terms; parish and LDEQ records control site and environmental status.
What is Louisiana data center power demand?
Louisiana data center power demand is a multi-gigawatt large-load issue controlled through the LPSC docket trail. U-37425 covers the approved first Meta Hyperion package; U-37882 covers the open Meta expansion package tied to more than 5,200 MW of additional generation and 500 kV transmission; U-37853 covers Waterford 6 and Westlake generation; and X-37921 is the large-load guideline repository.
What are the LPSC data center dockets to watch?
The four LouisianAI control dockets are U-37425 for Meta Hyperion Phase 1, U-37882 for Meta Hyperion Phase 2 / Project Evest, U-37853 for Entergy's Waterford 6 and Westlake generation request, and X-37921 for the LPSC large-load guidelines repository.
Which LPSC docket covers Meta Hyperion?
Meta Hyperion appears in U-37425 for Phase 1 and U-37882 for the expansion also described as Evest LLC or Project Evest. U-37425 has an approved settlement; U-37882 remained open in the LPSC docket details page as of May 15, 2026.
Do LPSC dockets show whether ratepayers pay for data center power?
The dockets are the public control surface for that question. They show the utility's proposed customer agreement, cost recovery, collateral, contract term, and intervenor positions, but some customer-specific MW and agreement terms can be redacted.