Regulatory tracker

LPSC data center dockets.

The plain-English control page for Louisiana Public Service Commission dockets tied to AI data center load, Entergy generation, transmission, customer agreements, ratepayer protection, and the LPSC permitting layer behind Louisiana data center power.

Start here: the docket trail decides who pays.

Announced data-center load is only useful after the LPSC record shows the utility package, customer agreement, tariff treatment, hearing posture, order status, and ratepayer-protection terms. This page keeps those filings connected to the project pages.

Last checked
2026-05-15

Source status comes from the LPSC public docket details pages and linked official filings. Open dockets are not treated as approved until the LPSC posts an order or certification decision.

Direct answer

What is Entergy Louisiana data center power?

Entergy Louisiana data center power is governed through the LPSC docket trail. U-37425 approved the first Meta Hyperion package; U-37882 seeks certification for more than 5,200 MW of additional generation plus 500 kV transmission, storage, nuclear uprates, and renewables; U-37853 is the broader Waterford 6 / Westlake generation filing.

What is Entergy Louisiana data center load?

Entergy Louisiana data center load is the large-load demand tied to Meta Hyperion, later Meta expansion filings, and broader Louisiana industrial growth. The control records are U-37425 for Meta Phase 1, U-37882 for the Meta expansion package, U-37853 for Waterford 6 / Westlake generation, and the LPSC large-load guideline repository X-37921.

What is Louisiana data center Entergy interconnection?

Louisiana data center Entergy interconnection means the regulatory and physical path for connecting large AI load to Entergy generation, substations, 500 kV transmission, customer agreements, collateral, and tariffs. For Meta Hyperion, U-37425 and U-37882 are the public controls for what can energize, who pays, and when the load can be served.

What is Hut 8 River Bend Louisiana data center power?

Hut 8 River Bend Louisiana data center power is an Entergy-served West Feliciana Parish question centered on the River Bend project profile, Entergy service, the public 245 MW anchor lease, and project/LPSC evidence for energization. It should not be confused with SWEPCO's Amazon Caddo/Bossier corridor.

Which utility powers Amazon AWS Caddo and Bossier data centers?

AEP SWEPCO is the utility of record for Amazon AWS Caddo and Bossier data centers. The canonical answer path is the Amazon project profile, the Amazon operator hub, the Caddo and Bossier parish hubs, and the power topic; the LPSC docket page remains the control surface for large-load tariff and ratepayer-protection context.

What is Louisiana data center peak power MW?

Louisiana data center peak power MW is not a single published IT-load number. The source-backed public proxy is the docketed utility build: U-37425 for Meta Phase 1, U-37882 for more than 5,200 MW of expansion generation and transmission, U-37853 for Waterford 6 and Westlake, plus project-level MW rows on LouisianAI.

What are Louisiana data center permits?

Louisiana data center permits combine parish zoning or site approval, LDEQ air and water permits where applicable, LPSC utility filings for power and tariffs, and federal reviews only when triggered. The LPSC page is the control surface for power permits and ratepayer terms; parish and LDEQ records control site and environmental status.

What is Louisiana data center power demand?

Louisiana data center power demand is a multi-gigawatt large-load issue controlled through the LPSC docket trail. U-37425 covers the approved first Meta Hyperion package; U-37882 covers the open Meta expansion package tied to more than 5,200 MW of additional generation and 500 kV transmission; U-37853 covers Waterford 6 and Westlake generation; and X-37921 is the large-load guideline repository.

LPSC source freshness
Last checked 2026-05-15. Basis: LPSC docket details and linked official filings. Review filing list.

Source status is pulled from filing pages. Open dockets are not treated as approved until the LPSC posts an order or certification decision.

Docket table

Four records drive the Louisiana AI power story.

Read load brief
DocketProjectUtilityCustomerStatusHearing / order controlRatepayer issue
U-37425
Meta Phase 1 / Laidley LLC
Meta Hyperion, Richland Parish
Entergy LouisianaLaidley LLC / Meta PlatformsApprovedSettlement approved at the August 20, 2025 LPSC Business and Executive Session; order document dated August 29, 2025.Whether the generation, transmission, solar procurement, collateral, and contract-term structure keeps Meta-specific infrastructure costs from being shifted to existing Entergy Louisiana customers.
U-37882
Meta Phase 2 / Evest LLC / Project Evest
Meta Hyperion expansion, Richland Parish
Entergy LouisianaEvest LLC / Meta PlatformsOpenOpen as of May 15, 2026; no final order posted in the LPSC docket details page.Whether the expanded electric service agreement, collateral package, and asset end-of-term treatment make Meta pay the full cost of new generation, transmission, storage, and interconnection infrastructure.
U-37853
Waterford 6 / Westlake generation
Waterford 6 and Westlake Power Station
Entergy LouisianaSystem resource / large-load growthOpenOpen as of May 15, 2026; no final certification order posted in the LPSC docket details page.Whether the new combined-cycle generation is treated as a broad system resource, a large-load-serving resource, or some blended recovery structure.
X-37921
Large-load non-binding guidelines
Large Load Additions framework
Louisiana Public Service CommissionAll large-load customersRepositoryInformational repository docket; LPSC states that no interventions will be accepted.The guidelines define the questions utilities and large-load customers must answer before new load is allowed to move quickly through the regulatory process.
Plain-English docket notes
U-37425

Meta Phase 1 / Laidley LLC

Approved

This is the first Meta Hyperion power docket. It approved the initial generation and transmission package needed to serve Meta's Richland Parish campus.

Why it matters
It is the canonical LPSC record for Meta Phase 1 and the source most likely to answer searches for Entergy Louisiana data center power, Meta Hyperion interconnection, and Richland Parish ratepayer protections.
Next watch
Track compliance filings, cost-allocation exhibits, transmission construction updates, and any later true-up or rider filings tied to the approved settlement.
Opened
2024-11-04
Published
2024-11-08
U-37882

Meta Phase 2 / Evest LLC / Project Evest

Open

This is the Meta expansion docket. Entergy describes the package as seven additional gas combined-cycle plants totaling more than 5,200 MW, roughly 240 miles of 500 kV transmission, storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables.

Why it matters
It is the main docket behind queries for Project Evest, Meta Hyperion 5GW Louisiana, the Lightning Amendment, and whether Meta's expansion leaves any tail-end cost risk for ratepayers.
Next watch
Track testimony, settlement posture, contested issues, intervention activity, and the eventual LPSC certification vote or order.
Opened
2026-03-26
Published
2026-03-27
U-37853

Waterford 6 / Westlake generation

Open

This docket is not a single-customer Meta docket. It covers Entergy's request to build Waterford 6 and Westlake generation resources that sit in the broader Louisiana large-load power stack.

Why it matters
It is the control docket for searches about Entergy Louisiana peak power MW, Waterford 6, Westlake Power Station, and the generation side of the AI-load buildout.
Next watch
Track certification schedule, cost-recovery design, in-service date exhibits, and any linkage between the resources and hyperscale customer agreements.
Opened
2026-02-24
Published
2026-02-27
X-37921

Large-load non-binding guidelines

Repository

This is the public repository for the LPSC's large-load guidelines. It is the framework used to evaluate expedited filings like U-37882.

Why it matters
It is the control record for searches about LPSC large load guidelines, Lightning Amendment filings, non-binding guidelines, and AI data center ratepayer protection.
Next watch
Track whether future LPSC orders cite the guidelines, modify them, or convert them into binding tariff or certification requirements.
Opened
2026-05-06
Published
2026-05-08
How to use this page

Treat it as a regulatory control surface, not legal advice.

LouisianAI uses this page to normalize docket numbers, aliases, source links, and ratepayer questions. For underwriting, cite the LPSC docket or primary document directly and treat LouisianAI as an independent index.

Source support

What the source cluster is proving.

SignalSupportsStatusSource
Meta phase 1 filingCanonical control record for approved phase 1 generation and transmission terms.Primary sourceOpen source
Meta phase 1 orderDecision-chain document for the phase 1 docket settlement.DecisionOpen source
Meta expansion filingOpen expansion docket for phase 2 load-service and utility terms.Active filingOpen source
Waterford 6 / Westlake contextReference filing for generation additions tied to large-load demand.ContextOpen source
LPSC large-load guidelinesRepository guidance for the non-binding large-load process.ReferenceOpen source
Sources
  1. [1]
    U-37425 docket details
    Louisiana Public Service Commission
    Open
  2. [2]
    U-37425 order document
    Louisiana Public Service Commission
    Open
  3. [3]
    U-37882 docket details
    Louisiana Public Service Commission
    Open
  4. [4]
    U-37853 docket details
    Louisiana Public Service Commission
    Open
  5. [5]
    X-37921 docket details
    Louisiana Public Service Commission
    Open
  6. [6]Open
  7. [7]
    LPSC large-load non-binding guidelines PDF
    Louisiana Public Service Commission
    Open
  8. [8]Open
  9. [9]Open