| U-37425 | Laidley LLC Meta Hyperion, Richland Parish | Entergy Louisiana | Laidley LLC / Meta Platforms | Approved | Current | Settlement approved at the August 20, 2025 LPSC Business and Executive Session; order document dated August 29, 2025. | Whether the generation, transmission, solar procurement, collateral, and contract-term structure keeps Meta-specific infrastructure costs from being shifted to existing Entergy Louisiana customers. |
| U-37882 | Evest LLC / Project Evest Meta Hyperion expansion, Richland Parish | Entergy Louisiana | Evest LLC / Meta Platforms | Open | Review due | Open certification proceeding. On August 12, 2026, the Commission voted 3-1 to reverse the ALJ ruling that had ordered Meta to produce additional analyses; written order U-37882-A is dated September 17, 2026. On September 16, the Commission accepted an attorneys'-eyes-only confidentiality agreement and vacated the ALJ's August 6 ruling; written order U-37882-B is dated October 16, 2026. Advocacy-party releases from the Alliance for Affordable Energy and Union of Concerned Scientists (represented by Earthjustice) state they filed a late-September 2026 appeal in the 19th Judicial District Court seeking reversal and reinstatement of the ALJ's July 10 partial subpoena order. An October 19, 2026 American Press report (by The Center Square) says the petition asks the court to reinstate the subpoena, halt activity on Entergy's application, reopen the evidentiary record, and expedite review before the Commission's scheduled December 16, 2026 consideration. WWL Louisiana's October 23, 2026 investigation (updated October 26) reports October 7 hearing testimony from Entergy regulatory-affairs director Ryan Jones, under cross-examination by Louisiana Energy Users Group attorney Carrie Tournillon, that other customers could face some costs if Meta exits early and that Entergy would seek rate recovery for assets still providing value. The same WWL report says Entergy's projected $4 billion in 20-year savings is "not a guarantee" under questioning, describes Entergy's claimed $1.9 billion immediate benefits (including $695 million storm/resilience, $140 million efficiency, and $60 million low-income support), and frames total proposed buildout costs at about $20 billion (~$13 billion plants plus ~$7 billion switching stations, batteries, and transmission). No court ruling has been reported; appeal status is pending. | Whether the expanded electric service agreement, collateral package, and asset end-of-term treatment make Meta pay the full cost of new generation, transmission, storage, and interconnection infrastructure. |
| U-37853 | Waterford 6 / Westlake generation Waterford 6 and Westlake Power Station | Entergy Louisiana | System resource / large-load growth | Open | Current | Open certification proceeding. An October 13, 2026 ruling granted Staff's unopposed schedule change setting pre-hearing briefs for October 23 and hearing dates for October 29 through November 2, 2026. The docket shows pre-hearing briefs filed October 23 by LPSC Staff, Entergy Louisiana, Sierra Club, and the Environmental Defense Fund, and by the Alliance for Affordable Energy on October 23 and 27. As of November 10, 2026 the newest docket entry is dated October 30, 2026 and no post-hearing filing or order is listed. | Whether the new combined-cycle generation is treated as a broad system resource, a large-load-serving resource, or some blended recovery structure. |
| X-37921 | Large-load non-binding guidelines Large Load Additions framework | Louisiana Public Service Commission | All large-load customers | Repository | Current | Informational repository docket, not an approval path. LPSC states that no interventions will be accepted; the public-comment window closed June 19, 2026. | The guidelines define the questions utilities and large-load customers must answer before new load is allowed to move quickly through the regulatory process. |
| R-37905 | Private-use electrical networks for new large loads Private-use electrical network framework | Louisiana Public Service Commission | Prospective large-load customers | Open | Current | Open notice proceeding. Staff filed a first report and recommendation with a first draft rule on August 14, 2026; a technical conference followed on August 28; comments were due September 25. The official LPSC docket lists a Nov. 4, 2026 filing, document F26-84881, titled "Staff's Final Report and Recommendation Containing Staff's Final Proposed Rules Issued by Deputy General Counsel Lauren T. Evans"; a Nov. 16, 2026 filing, document F26-84985, titled "Correspondence to Oppose the Form of the Final Proposed Rules for Private Use Electrical Networks" for the Louisiana Energy Users Group, the Louisiana Chemistry Association, and Louisiana Mid-Continent Oil and Gas Association; and a Nov. 17, 2026 filing, document F26-84995, titled "Correspondence Regarding the LPSC's Final Proposed Rules for Private Use Electrical Networks for Powering Prosperity." The LPSC's revised Nov. 18, 2026 Business and Executive Session agenda listed Exhibit 2 as discussion and possible vote on the R-37905 Proposed Final Rule. WBRZ reports that at the Nov. 18, 2026 session the private-use electrical-network agenda item was deferred to the Commission's next meeting, Dec. 16, 2026, at the Shreveport Commission Building. As of November 19, 2026, no final rule has been adopted. Official Nov. 18, 2026 minutes and transcript were awaiting publication on the LPSC site as of that date. | Whether private-use generation and network arrangements for prospective large loads remain legible to the Commission and do not shift costs, reliability exposure, or network obligations to existing utility customers. |
| U-38035 | Cleco / Applied Digital service package Applied Digital data-center campus, Rapides Parish | Cleco Power LLC | Applied Digital | Open | Current | Open certification proceeding. Cleco's filing seeks approval of an electric service agreement, a capacity contract with Tenaska through May 31, 2037, and related generation and grid-connection support. On September 16, 2026, the Commission unanimously set consideration no later than the March 2027 Business and Executive Session, with an October 15 written order directing the ALJ to compile the record without recommendation and setting hearing dates for January 26-27, 2027. | Whether the Cleco/Applied Digital service structure, proposed generation support, and long-term capacity contract keep dedicated large-load costs and end-of-term risk from shifting to existing customers. |