Source-of-record register

4 source-backed records. 2 watch-list rows. One visible rule.

The tracker has 6 records: 3 named campus records and 1 multi-campus program, all source-backed and included once in the statewide capex, published-power, parish, and operator denominator; plus 2 visible watch-list rows excluded from those totals. Generation, transmission, storage, and renewables are tracked separately in the LPSC docket trail and are not data-center rows.

All tracker records

6

Core source-backed records

4

Watch-list records

2

RecordStatusClassParishConfidenceCounting rule
Meta Hyperion AI Data Center

July 13, 2026: Meta confirmed 5 GW / $50B+ build-out; U-37882 expansion package still under LPSC review.

Under constructioncampusRichlandBSource-backed campus record; included in statewide capex, published-power, parish, and operator totals.
Amazon NW Louisiana Cluster

Bossier final plat approved; linked Caddo/Bossier cluster.

AnnouncedprogramCaddo & BossierBSource-backed multi-campus program; its announced investment is counted once, while unfiled sub-sites and undisclosed MW stay out of the denominator.
Hut 8 River Bend Campus

330 MW utility capacity; $16M parish water works announced May 2026.

Under constructioncampusWest FelicianaCSource-backed campus record; included in statewide capex, published-power, parish, and operator totals.
Delta Forge 1

Delta Forge 1 broke ground Jan. 2026; mid-2027 target.

Under constructioncampusRapidesCSource-backed campus record; included in statewide capex, published-power, parish, and operator totals.
STACK Bossier site context

Potential subsite within Amazon/STACK's $12B multi-campus program; independent cost and MW are not public.

WatchwatchBossierDWatch-list record; excluded from statewide capex, published-power, parish, operator, and map totals until a public record hardens.
Vantage East Bank

Unconfirmed; tracked from supplier RFPs only.

RumouredwatchEast Baton RougeDWatch-list record; excluded from statewide capex, published-power, parish, operator, and map totals until a public record hardens.
Weekly record updates

Get the source-linked change, not a speculation alert.

The weekly brief reports what changed, the supporting source/date, remaining uncertainty, and the next public record to watch.