LIVEResearch desk operatingU-37425Entergy LA filing · 7.2 GW load additionRICHLANDHyperion phase 3 permit acceptedCADDOSTACK substation civil mobilisingW. FELICIANAHut 8 River Bend hearing 06/03
Source-of-record register

Five confirmed records. One watch-list record. One visible rule.

The tracker has 6 records: 5 confirmed infrastructure records included in campus, capex, MW, parish, and operator totals, plus 1 rumour-grade watch record retained for research continuity but excluded from those totals.

All tracker records

6

Confirmed records

5

Watch-list records

1

RecordStatusClassParishConfidenceCounting rule
Meta Hyperion AI Data Center

July 13, 2026: Meta confirmed 5 GW / $50B+ build-out; U-37882 expansion package still under LPSC review.

Under constructionconfirmedRichlandBIncluded in confirmed campus and capex totals.
Amazon NW Louisiana Cluster

Bossier final plat approved; linked Caddo/Bossier cluster.

AnnouncedconfirmedCaddo & BossierBIncluded in confirmed campus and capex totals.
Hut 8 River Bend Campus

245 MW lease; $16M parish water works announced May 2026.

Under constructionconfirmedWest FelicianaCIncluded in confirmed campus and capex totals.
Delta Forge 1

Delta Forge 1 broke ground Jan. 2026; mid-2027 target.

Under constructionconfirmedRapidesCIncluded in confirmed campus and capex totals.
STACK Infrastructure Bossier

Co-located near the Amazon cluster.

Civil worksconfirmedBossierBIncluded in confirmed campus and capex totals.
Vantage East Bank

Unconfirmed; tracked from supplier RFPs only.

RumouredwatchEast Baton RougeDWatch-list record; excluded from confirmed campus totals until a public record hardens.
Weekly record updates

Get the source-linked change, not a speculation alert.

The weekly brief reports what changed, the supporting source/date, remaining uncertainty, and the next public record to watch.