LIVEResearch desk operatingU-37425Entergy LA filing · 7.2 GW load additionRICHLANDHyperion phase 3 permit acceptedCADDOSTACK substation civil mobilisingW. FELICIANAHut 8 River Bend hearing 06/03
Infrastructure tracker

Louisiana AI data center tracker.

Start here: the tracked buildout in one paragraph.

LouisianAI tracks the live Louisiana AI data-center buildout by operator, parish, status, capex, peak MW, water exposure, LPSC docket posture, and source-linked project page. Use the rows below to move from statewide scale to the exact filing, operator, or permit trail behind each campus.

6 projects · $39.3B aggregate capex · 7,350 MW peak (mid-est.) · edition 2026.06.23
TableMapTimelineJSON
Capex tracked
$39.3B
Peak MW (sum)
7,350
Active builds
2 / 6
LPSC dockets
2 open / 4
Operators
6
Parishes
5
Filter
Filter data center tracker rows
Sort and density controls
Export CSV

What is the Louisiana AI infrastructure tracker?

The Louisiana AI infrastructure tracker is LouisianAI's source-cited register of every tracked AI and hyperscale data center project in the state: operator, parish, status, capex, peak MW, timeline posture, confidence level, and links to project-level evidence.

What is the Louisiana data center timeline?

The Louisiana data center timeline starts with Meta Hyperion under construction for initial 2027 operations and ramp through 2030, then Amazon/STACK's 2027-2028 northwest Louisiana campuses, Hut 8 River Bend Phase 1 in 2027, and Applied Digital Project Lightning in early development with no firm public power-on date.

What is Louisiana data center power demand?

Louisiana data center power demand is already multi-gigawatt: quantified tracker rows sum to roughly 6.7 GW, and the broader announced/planned AI pipeline exceeds 8 GW when later-stage load is included. The LPSC docket trail decides which generation and transmission projects can energize that load.

What is Louisiana data center capex announced?

Louisiana data center capex announced depends on the layer being cited. The row-level tracker on this page shows roughly $39.3B of source-linked project capex, while the statewide overview carries the broader $60B+ announced pipeline answer when later expansion framing is included. Each row links to the project profile behind the capex number.

What data infrastructure exists in New Orleans, LA?

New Orleans data infrastructure in this tracker is operational colocation: EdgeConnex New Orleans and Fogo New Orleans in Orleans Parish. The hyperscale AI campuses driving most new Louisiana power demand are outside New Orleans.

What is Meta Hyperion data center status in 2026?

Meta Hyperion is under construction in Richland Parish in 2026. It is the largest tracked Louisiana AI data center, with a 2 GW initial profile and a public expansion path toward 5 GW.

Which operators are building Louisiana AI data centers?

The Louisiana operator set is Meta in Richland Parish, Amazon Web Services with STACK in Caddo and Bossier Parishes, Hut 8 at River Bend in West Feliciana Parish, Applied Digital at Project Lightning in Rapides Parish, plus operational colocation operators in Baton Rouge and New Orleans.

What is Louisiana data center water and environmental impact?

Louisiana data center water and environmental impact is project-specific: cooling design, permitted withdrawals, discharge path, parish water agreements, and LDEQ/LPSC records. Meta Hyperion has the most visible water-use record; Amazon has regional water-infrastructure commitments; Hut 8 and Applied Digital require site-level permit tracking.

Analytics

The buildout, visualized.

Interactive breakdowns of capex allocation, power demand, project status, parish concentration, and operator portfolios across all tracked Louisiana AI infrastructure.

Projects loaded
6
Aggregate capex
$39.3B
Aggregate MW
7,350 MW
Under construction
1
Confidence A+B
3
Capex by project
Amazon NW Louisiana Cluster12.0B
Amazon / STACK
Meta Hyperion AI Data Center10.0B
Meta Platforms
Hut 8 River Bend Campus10.0B
Hut 8
STACK Infrastructure Bossier4.5B
STACK Infrastructure
Applied Digital Lightning2.0B
Applied Digital
Vantage East Bank800M
Vantage Data Centers
Peak MW demand by project
Amazon NW Louisiana Cluster~3,000
Amazon / STACK
Meta Hyperion AI Data Center2,000
Meta Platforms
Hut 8 River Bend Campus1,500
Hut 8
STACK Infrastructure Bossier750
STACK Infrastructure
Vantage East Bank100
Vantage Data Centers
Status distribution
Under construction1 (17%)
Civil works1 (17%)
Permitting1 (17%)
Site acquired1 (17%)
Announced1 (17%)
Rumoured1 (17%)
Confidence ladder
Grade A
0 projects
0%
Grade B
3 projects
50%
Grade C
2 projects
33%
Grade D
1 projects
17%
Operator portfolio
Amazon / STACK1 project · $12.0B · 3,000 MW
Meta Platforms1 project · $10.0B · 2,000 MW
Hut 81 project · $10.0B · 1,500 MW
STACK Infrastructure1 project · $4.5B · 750 MW
Applied Digital1 project · $2.0B · 0 MW
Vantage Data Centers1 project · $800M · 100 MW
Parish concentration
Caddo & Bossier1 project · 12.0B
3,000 MW
Richland1 project · 10.0B
2,000 MW
West Feliciana1 project · 10.0B
1,500 MW
Bossier1 project · 4.5B
750 MW
Rapides1 project · 2.0B
0 MW
East Baton Rouge1 project · 0.8B
100 MW
Tracking momentum by cohort year
20241 projects · $10.0B · 2,000 MW
20253 projects · $26.5B · 5,250 MW
20262 projects · $2.8B · 100 MW
Capex vs MW landscape
0M3.0B6.0B9.0B12.0B0750 MW1,500 MW2,250 MW3,000 MWAmazon NW Louisiana ClusterMeta Hyperion AI Data CenterCapex (scaled)MW (scaled)
  • Amazon NW Louisiana Cluster — Amazon / STACK ($12B, ~3,000 MW, Announced)
  • Meta Hyperion AI Data Center — Meta Platforms ($10B+, 2,000 MW, Under construction)
  • Hut 8 River Bend Campus — Hut 8 ($10B, 1,500 MW, Permitting)
  • STACK Infrastructure Bossier — STACK Infrastructure ($4.5B, 750 MW, Civil works)
  • Vantage East Bank — Vantage Data Centers ($800M, 100 MW, Rumoured)

Values use published tracker capex and MW fields.

Geography

Active build, in geography.