Skip to main content
  • R-37905: LPSC defers private-network rule item to December 16
  • Jefferson Davis Parish data-center regulation ordinance
  • Nonprofit suit challenging LPSC lightning directive
  • Rapides Parish England Authority PILOT lease vote for Applied Digital Delta Forge 1
  • Beauregard Parish data-center moratorium
  • Louisiana Public Service Commission District 1 and District 5 election
Tracker / Cameron Parish / Cameron Generation, LLC
Share on XShare on LinkedIn
Application filedInitial Title V and PSD review pendingConf · BUnverified

Cameron Campus Data Center No. 2 application.

Cameron Generation, LLC identifies itself in its October 15, 2026 application as a wholly owned Venture Global LNG, Inc. subsidiary. The applicant proposes three power islands of up to 720 MW each, totaling up to 2,160 MW of generation, for nearby Cameron Campus Data Center No. 1. That separate campus is described as ten data-center buildings with its own 720 MW power island. The No. 2 facility is proposed north of Marshall Street and east of Wakefield Road and the Calcasieu Ship Channel. The environmental assessment estimates more than $1 billion in proposed project investment. The expedited-review request estimates approximately 115 permanent jobs. The application’s environmental assessment gives both 115 and 150 permanent jobs in different passages. LDEQ found the initial Title V and PSD applications administratively complete on October 19 and approved expedited processing. Final permit issuance, construction and operating status, campus IT load, tenant and actual investment remain unverified.

What matters first for Cameron Campus Data Center No. 2 application

Cameron Campus Data Center No. 2 application is tracked here by status, operator, parish, power, capex, source-backed claims, and the next public records needed before a claim should be treated as verified.

Answers cite desk records only. Search instead

Verification needed · Not disclosed · last sync
Operator
Cameron Generation, LLC
Parish
Cameron Parish
Utility
Not disclosed in the application notice
Peak MW
Verification needed
Capex
Not disclosed
Sq ft
Verification needed
Acres
Verification needed
Confidence
B
Desk thesis

Why Cameron Campus Data Center No. 2 application campus load drives the power story.

Cameron Generation, LLC identifies itself in its October 15, 2026 application as a wholly owned Venture Global LNG, Inc. subsidiary. The applicant proposes three power islands of up to 720 MW each, totaling up to 2,160 MW of generation, for nearby Cameron Campus Data Center No. 1. That separate campus is described as ten data-center buildings with its own 720 MW power island. The No. 2 facility is proposed north of Marshall Street and east of Wakefield Road and the Calcasieu Ship Channel. The environmental assessment estimates more than $1 billion in proposed project investment. The expedited-review request estimates approximately 115 permanent jobs. The application’s environmental assessment gives both 115 and 150 permanent jobs in different passages. LDEQ found the initial Title V and PSD applications administratively complete on October 19 and approved expedited processing. Final permit issuance, construction and operating status, campus IT load, tenant and actual investment remain unverified.

Source-linked claim table
ClaimValueSource
Capex rangeNot disclosed [1][2][3]+12Louisiana Department of Environmental Quality
Power capacityVerification needed [1][2][3]+12Louisiana Department of Environmental Quality
Site sizeVerification needed · Verification needed [1][2][3]+12Louisiana Department of Environmental Quality
JobsNot yet verified against a public source verify—
Louisiana incentive postureAct 730 sales/use tax exemption and local PILOT structures require document-level verification. [16]Louisiana Legislature
Sales/use tax and PILOT frameworkLouisiana Act 730 and local PILOT structures are tracked as separate legal/economic artifacts. [16]Louisiana Legislature
Chronology

Cameron Campus Data Center No. 2 application on the public record.

  1. Nov 11, 2026
    Publicly announced
Diligence · Power & interconnection

Data-center power and interconnection record, basis by basis.

Not disclosed in the application notice · Verified November 18, 2026

Load bases are modeled separately and are never summed, averaged, or normalized into a single MW figure. Any basis without a named public source is recorded as not-in-public-record rather than estimated. Every populated value carries its own source; every basis without one is held explicitly as not in public record.

Load bases — six separate figures, never one

Requested

Not in public record

Contracted

Not in public record

Design capacity

Not in public record

Utility-deliverable

Not in public record

Critical IT

Not in public record

In service

Not in public record

Service & offtake agreements

Agreements

Not in public record

No named service, interconnection, or offtake agreement is in the reviewed public record for this project.

Queue position

Not in public record

No public interconnection queue position.

Energization

Energization dates

Not in public record

No public energization or operations-commencement date for this project.

Grid dependencies

Substations

Not in public record

No named substation dependency is in the public record for this project.

Transmission

Not in public record

No named transmission dependency is in the public record for this project.

Generation & storage

Not in public record

No dedicated generation or storage dependency is in the public record for this project.

Rate, tariff & curtailment

Rate / tariff posture

Not in public record

No tariff or rate posture in the public record.

Curtailment risk

Unknown

No interruptibility, curtailment, or demand-response terms for this load appear in the reviewed public record; the risk is not assessed rather than assumed low.

Diligence · Permits & regulatory

Data-center permit and regulatory workflow, record by record.

Verified September 23, 2026

Each row is one dated public record — or an explicit not in public record monitoring marker where no filing could be located. Rows never imply a permit exists without a linked source.

  1. 2026-10-15Under reviewLDEQ air
    Cameron Campus No. 2 — initial Title V and PSD air applications

    Next: Technical review, draft permits, public participation notices and final LDEQ decisions. The six records supplied under public-records request 109177 include the application, administrative completeness and expedited-processing documents. An issued final Title V or PSD permit remains unverified.

Diligence · Water & environmental

Data-center water and environmental record, field by field.

Verified November 19, 2026

Every field below carries its own source or is held explicitly as not in public record. Cooling designs, withdrawal sources, and volumes are never inferred from nearby plants, river adjacency, or typical hyperscale designs.

Cooling

Cooling method

Not in public record

Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.

The applicant proposes air cooling for the No. 2 generation equipment (application PDF pages 598 and 625). The separate No. 1 data-center buildings are described as using direct-to-chip closed-loop cooling (page 596). These statements describe proposed equipment at different sites.

Louisiana Department of Environmental Quality · 2026-10-15 ↗

Withdrawal & discharge

Withdrawal source

Not in public record

Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.

Discharge destination

Not in public record

Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.

Authorized volumes

Not in public record

No daily-gallon authorization is filed at project level. Monitored through LDEQ water-permit notices, Conservation and Energy groundwater records, and parish water-board minutes.

Permits & agreements

Water / wastewater permits

Not in public record

Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.

Water-board / supply agreements

Not in public record

No parish water-board or supply agreement is in the public record. Monitored through parish water-board minutes and police-jury agendas.

Risk & exposure

Water stress

Not in public record

The applicant's Environmental Assessment Statement anticipates no adverse impact on the Chicot aquifer from the proposed demand and discusses nearby aquifer testing (application PDF page 607). An independent site-specific water-stress determination remains unverified.

Louisiana Department of Environmental Quality · 2026-10-15 ↗

Flood & hurricane

Flood zone: Zone AE, as described in the applicant's EAS

Hurricane exposure: The applicant describes the site as a FEMA Special Flood Hazard Area and proposes a surrounding floodwall for coastal flooding plus a hydrologic modification assessment during coastal permitting (application PDF page 611). The floodwall is proposed.

Reported
Louisiana Department of Environmental Quality · 2026-10-15 ↗

Wetlands

The applicant anticipates effects on jurisdictional wetlands and plans a wetlands delineation and joint USACE Section 404 and Coastal Use Permit application (application PDF page 609). A completed jurisdictional delineation and issued approvals remain unverified.

Pending
Louisiana Department of Environmental Quality · 2026-10-15 ↗

Emissions / air

LDEQ found the initial Title V and PSD air applications administratively complete on October 19, 2026. The reviewed application describes proposed generation equipment and modeled emissions. Permit issuance and authorized emissions remain unverified.

Pending
Louisiana Department of Environmental Quality · 2026-10-19 ↗

Waste streams

The applicant anticipates industrial waste such as blowdown wastewater, maintenance debris, spent catalyst and, if onsite treatment is used, reverse-osmosis and ultrafiltration filter cake. It also anticipates hazardous maintenance wastes including spent solvents, degreasers, paint wastes and vessel-cleanout materials, with offsite recycling or disposal through licensed facilities and transporters (application PDF pages 609–610). These are planned waste-management arrangements.

Reported
Louisiana Department of Environmental Quality · 2026-10-15 ↗

Environmental review

Review status

Air applications administratively complete with permit decisions pending

Pending

The reviewed October 15 application includes an Environmental Assessment Statement. PDF page 607 estimates No. 2 turbine, heat-recovery steam-generator and miscellaneous water demand at approximately 0.8–1.2 million gallons per day, supplied by treated onsite wells or parish waterworks. Pages 607–610 anticipate groundwater, health, wastewater, USACE and coastal approvals, including LPDES review of reverse-osmosis and ultrafiltration residual discharge. Those statements describe future permitting work and applicant estimates. LDEQ's October 19 administrative completeness determination and expedited processing approval leave the air permit decisions pending.

Louisiana Department of Environmental Quality · 2026-10-15 ↗
Diligence · Real estate & community impact

Data-center land, incentive, and community-impact record.

Verified November 18, 2026

Land deals, incentive terms, contractor awards, and community exposure each carry a named source or are held explicitly as not in the public record. Construction and operations jobs are never merged, and no dollar figure is estimated without a published record.

Land & assessed value

Land transactions

Not in the public record

No project-level land transaction is in the public record for this profile.

Assessed value

Not in the public record

The air application notice supplies no assessed value.

Incentives & tax

Incentive terms

Not in the public record

No project-specific incentive term is in the public record. Statewide program rules live on the incentives pages.

Taxable-value implications

Not in the public record

The site’s taxable value is undisclosed.

Method: An air application does not establish a tax assessment or an incentive award.

Construction & contractors

Construction packages

Not in the public record

No project-level construction package is in the public record for this profile.

Contractor awards

Not in the public record

No contractor award is in the public record for this project; awards are monitored through parish bid postings and operator announcements.

Jobs & workforce

Construction jobs

Not in the public record

No site-specific construction jobs figure is disclosed.

Operations jobs

Not in the public record

No site-specific operating jobs figure is disclosed.

Workforce availability

Not in the public record

No site-specific workforce agreement is disclosed.

Community exposure

Lodging & housing pressure

Not in the public record

No site-specific housing impact is disclosed.

Roads & public services

Not in the public record

No road or public-service impact is in the public record for this profile.

Local tax-base exposure

Not in the public record

No site-specific tax estimate is disclosed.

Project diligence

Open questions and controlling records

Open printable evidence packet

Power and load

not in public record
Current record
No project-specific LPSC control record is linked in this public packet.
Next record to watch
Utility service agreement, interconnection filing, transmission record, or LPSC docket.
Review power and load context

Permits and site controls

watch
Current record
No controlling parish permit or site-plan record is linked in this packet.
Next record to watch
Parish agenda, site-plan approval, zoning packet, or environmental permit notice.
Review permits and site controls context

Water and cooling

watch
Current record
No project-specific withdrawal, cooling, or water-service record is linked in this packet.
Next record to watch
LDEQ notice, groundwater/water-board record, utility agreement, or operator environmental disclosure.
Review water and cooling context

Construction and delivery

watch
Current record
Application filed · Initial Title V and PSD review pending
Next record to watch
Operator construction milestone, utility energization evidence, parish inspection, or filed completion notice.
Review construction and delivery context

Evidence gaps

Project and operator
Cameron Campus Data Center No. 2 application · Cameron Generation, LLC · reportedOpen the linked record before repeating a material claim.
Parish and utility
Cameron Parish · Not disclosed in the application notice · reportedUtility territory is context, not proof of an executed service agreement or energization date.
Current tracker status
Application filed · Initial Title V and PSD review pending · watchStatus is a source-labelled tracking assessment. Open regulatory records are not approvals.
Tracked capital investment
Not disclosed · reportedInvestment is a tracked public figure, not a completed-spend assertion.
Tracked power capacity
Not in the public record · not-in-public-recordCapacity, contracted load, utility design, critical IT load, and in-service power are distinct concepts.
Economic impact calculator

Economic impact assumptions for Cameron Campus Data Center No. 2 application.

Edit the inputs to compare an ad-valorem proxy against a PILOT discount, construction labor hours, and peak power demand relative to an editable parish consumption baseline.

Ad-valorem proxy

$0

PILOT proxy

$0

Construction job hours

0

Demand vs parish use

0x

What to watch next

Next Cameron Campus Data Center No. 2 application filings to watch.

  • LPSC docket activity for generation, transmission, and rate-base recovery tied to data-center load.
  • Cameron Parish permit, council, police jury, and economic-development agendas.
  • Operator press rooms, SEC filings, and investor presentations for delivery dates, lease economics, and tenant commitments.
  • Utility substation, transformer, and transmission-procurement signals near the site.
  • Workforce board, contractor, and supplier notices that usually precede peak construction demand.
Power and ratepayer questions roll up through the LPSC data center docket tracker, which normalizes the active filings and source links.
FAQ

Cameron Campus Data Center No. 2 application FAQ.

How big is Cameron Campus Data Center No. 2 application?

Cameron Campus Data Center No. 2 application is tracked at Verification needed and Verification needed, with Verification needed of power capacity where public sources support the number.

How many jobs will Cameron Campus Data Center No. 2 application create?

Current tracked figures show Verification needed permanent jobs and Verification needed construction jobs, subject to source verification.

What is the PILOT agreement for Cameron Campus Data Center No. 2 application?

A PILOT is a payment-in-lieu-of-taxes structure negotiated locally; this page tracks the public artifacts needed to compare ad-valorem exposure with negotiated payments.

When will Cameron Campus Data Center No. 2 application come online?

Application filed. Exact phase delivery dates remain tied to operator updates, utility milestones, parish permits, and regulatory filings.

Which parish is Cameron Campus Data Center No. 2 application in?

Cameron Campus Data Center No. 2 application is tracked in Cameron Parish, Louisiana.

Who is the operator of Cameron Campus Data Center No. 2 application?

Cameron Generation, LLC is the operator listed for Cameron Campus Data Center No. 2 application.

How much water will Cameron Campus Data Center No. 2 application use?

Water use is tracked as a verification item because definitive cooling and withdrawal figures usually appear in permits, utility exhibits, or operator environmental disclosures.

What incentives did Louisiana give Cameron Generation, LLC?

Louisiana data-center incentives can include Act 730 sales/use tax treatment and local PILOT structures; the exact package should be verified against state, parish, and operator documents.

What power infrastructure serves Cameron Campus Data Center No. 2 application?

The page tracks substations, transmission watch corridors, and utility filings as source-backed signals rather than engineering-grade interconnection maps.

Why does LouisianAI label confidence levels?

Confidence labels distinguish seed, reported, and verified claims so readers can separate early intelligence from document-backed facts.

Keep reading

Guides to following this project

Subscribe

Cameron Campus Data Center No. 2 application milestone alerts.

Cite this page or subscribe to filings that mention Cameron Campus Data Center No. 2 application.

By submitting, you ask LouisianAI to use this information for this request as described in the Privacy Notice.

Cited sources · 16 linked

Sourced public record for Cameron Campus Data Center No. 2 application.

[1]
Primary recordLouisiana Department of Environmental Quality · 2026-10-15
Open →
[2]
Primary recordLouisiana Department of Environmental Quality · 2026-10-19
Open →
[3]
Primary recordLouisiana Department of Environmental Quality · 2026-10-15
Open →
[4]
Primary recordLouisiana Department of Environmental Quality · 2026-10-21
Open →
[5]
Primary recordLouisiana Department of Environmental Quality · 2026-10-22
Open →
[6]
Primary recordLouisiana Department of Environmental Quality · 2026-11-11
Open →
[7]
ReportingLouisiana Department of Environmental Quality · 2026-11-08
Open →
[8]
Primary recordLouisiana Department of Environmental Quality · 2026-10-15
Open →
[9]
Primary recordLouisiana Department of Environmental Quality · 2026-10-19
Open →
[10]
Primary recordLouisiana Department of Environmental Quality · 2026-10-15
Open →
[11]
Primary recordLouisiana Department of Environmental Quality · 2026-10-21
Open →
[12]
Primary recordLouisiana Department of Environmental Quality · 2026-10-22
Open →
[13]
Primary recordLouisiana Department of Environmental Quality · 2026-11-11
Open →
[14]
ReportingLouisiana Department of Environmental Quality · 2026-11-08
Open →
[15]
LouisianAI methodology

LouisianAI methodology and reuse guardrails; not an independent project fact source.

ReportingLouisianAI
Open →
[16]
Louisiana Legislature bill and Act search for Act 730 data-center exemptions

Primary state-law lookup surface for Act 730 sales/use tax exemption and local PILOT diligence.

Primary recordLouisiana Legislature
Open →