Meta Hyperion AI Data Center
Under construction. July 13, 2026: Meta confirmed 5 GW / $50B+ build-out; U-37882 expansion package still under LPSC review.
Project profile →— residents. — sq mi. Population center: Rayville. As of May 2026 the parish hosts 1 tracked AI infrastructure project under Entergy Louisiana.
Source-backed rows on this hub: Meta Hyperion AI Data Center (Under construction — Phase II power expansion remains under LPSC review). The utility of record is Entergy Louisiana. Capex, megawatts, jobs, and permit outcomes stay on the named campus pages; this parish page does not invent a local total from those rows.
Rayville is the parish seat. LED's December 4, 2024 release places Meta's 2,250-acre former Franklin Farm site between Rayville and Delhi, about 30 miles east of Monroe. LouisianAI treats Meta data center Rayville LA, Richland Parish Meta data center, and Hyperion as the same campus. Official Meta campus materials are on datacenters.atmeta.com/richland-parish-data-center.
Each claim below is copied from an existing desk record and linked to that record’s source. Sections with no sourced item are left out.
Under construction. July 13, 2026: Meta confirmed 5 GW / $50B+ build-out; U-37882 expansion package still under LPSC review.
Project profile →Preliminary sketch plan recommended October 5, 2026 (pending documents and engineer review); reported by local newspaper. Richland Parish Police Jury reporting says jurors approved recommendations on four preliminary sketch plans at the October 5, 2026 meeting, including a proposed Oppidan Data Center on Highway 583 north of Herring Road (25 acres), pending all required documents and parish-engineer questions. This is a preliminary sketch-plan recommendation, not a final plat, permit, or zoning approval.
Richland Parish data-center hub →Proposed / reported; no final permit reported. Richland Beacon-News reported an October 1, 2026 LDEQ hearing on proposed operating, PSD, and acid-rain permits for Entergy's Richland Parish Units 3 and 4 (two combined-cycle units). This update did not independently retrieve an LDEQ notice, so the status is kept as reported/proposed only.
Approved. This is the first Meta Hyperion power docket. It approved the initial generation and transmission package needed to serve Meta's Richland Parish campus.
Docket record →Open. This is the Meta expansion docket. Entergy describes the package as seven additional gas combined-cycle plants totaling more than 5,200 MW, roughly 240 miles of 500 kV transmission, storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables. WWL Louisiana reports October 7 hearing testimony that some end-of-term or early-exit costs could still fall to other customers, and that Entergy's projected 20-year customer savings are not guaranteed under cross-examination.
Docket record →Operations: 500 — LED's December 2024 announcement frames 500+ permanent roles at full scale; Sherwood News reports the company expects roughly 300–500 operational full-time employees after construction finishes.. Construction: 5,000 — Meta frames more than 5,000 skilled-trade workers on-site at peak construction (Sherwood News).. Training: River Parishes Community College trades pipeline (desk record); LED FastStart
Parish jobs topic →Mortenson · Rayville, LA
Mortenson careers (official posting) →Mortenson · Rayville, LA
Mortenson careers (official posting) →Mortenson · Rayville, LA
Mortenson careers (official posting) →Mortenson · Rayville, LA
Mortenson careers (official posting) →Louisiana Delta Community College. Four-week entry-level program with BLS, OSHA 10, CORE, NSC Lift Truck, and Corning fiber-optic splicing certifications; cost and dates on the LDCC page.
Program source →Louisiana Delta Community College / Meta. $5 million Meta gift for full scholarships for Richland Parish high school graduates, starting with the Class of 2026, in data center-related trade programs. LDCC says details are coming.
Program source →Louisiana Delta Community College. Four-week LDCC program covering NCCER Core plus Construction Craft Laborer Level 1 with OSHA 10, BLS, and lift-truck training; WWNO reports it was created for Meta-site hiring demand.
Program source →A Grow NELA release summarizing an updated Ginovus economic-impact study commissioned by the regional economic-development organization after Meta's Richland Parish expansion announcement.
Grow NELA (commissioned study prepared by Ginovus) →An 88-page report prepared by Crenshaw Analytics for the 2026 Northeast Louisiana Economic Summit hosted by BRIP with the University of Louisiana Monroe and Grow NELA, covering 12 parishes and placing Meta's Richland Parish data-center impact in regional context.
Crenshaw Analytics (Michael Crenshaw) →A dated advocacy-oriented analysis by Synapse Energy Economics summarizing expert testimony filed on behalf of Sierra Club in Louisiana Public Service Commission Docket U-37882.
Synapse Energy Economics →A September 1, 2026 issue brief examining how Louisiana's data-center buildout intersects with the state's limited water-management framework, covering on-site cooling demand, groundwater well registration, and indirect water use from power generation.
Tulane Institute on Water Resources Law & Policy →A policy-convening white paper summarizing participant perspectives from the April 2026 Powering Louisiana Forum; the paper notes these views are not the author's personal opinions.
Kathleen Babineaux Blanco Public Policy Center; Powering Louisiana; Southeastern Wind Coalition; Greater New Orleans, Inc. →Region hub: Monroe Metro. Other parishes in the Northeast region:
LouisianAI currently tracks 1 announced or under-construction AI data center project in Richland Parish: Meta Hyperion AI Data Center.
Entergy Louisiana is the utility of record for Richland Parish. Project-specific generation and transmission costs are recovered from the data center customer under tariffs filed with the LPSC.
Richland Parish sits in the Northeast Louisiana region, with parish seat in Rayville.
The sourced Richland Parish data center is Meta Hyperion near Rayville. LED places the 2,250-acre former Franklin Farm site between Rayville and Delhi, about 30 miles east of Monroe.