Terrebonne Parish digital factory opportunity meeting
Public discussion and due diligence documented. Campus approval remains unverified
Terrebonne Parish Consolidated Government states that it held a community meeting at Fletcher Community College on October 22, 2026 about potential digital factory opportunities and impacts. Its presentation describes rural digital factory due diligence during April through October 2026. This source establishes a parish discussion, without confirming an approved campus, tenant or operating capacity. Primary documents checked November 18, 2026.
Terrebonne Parish source-linked watch →Rapides Parish England Authority PILOT lease vote for Applied Digital Delta Forge 1
Introduced unanimously Nov. 9, 2026; final discussion and approval vote scheduled Nov. 19, 2026 (pending)
KALB reports the England Industrial and Economic Development District (England Authority) unanimously voted on Monday, Nov. 9, 2026 to introduce a Payment In Lieu Of Taxes (PILOT) lease agreement for Applied Digital's 300 MW Delta Forge 1 campus near Boyce; the agreement names the counterparty as APLD AEX-01 LLC. KALB and Alexandria Town Talk both report final discussion and approval is scheduled for the Authority's Nov. 19 regular meeting. KALB reports the draft PILOT projects up to $575,497,500 for local taxing bodies through 2052, with payments beginning when signed ($13.8 million in 2026 and 2027, and $38,084,900 in 2028), and sets employment targets of 75 by 2028, 100 for 2029-2030, and 200 from 2031 at at least 150% of Louisiana's average wage (about $91,000 for 2026) with a 1.8x shortfall adjustment formula. The same report says the lease term is 15 years with two five-year extension options; includes a $50 million regional community benefit trust (2026-2040) plus a $4 million Boyce community-benefit schedule (2028-2030); and requires road repairs within 180 days after construction, ISO Public Protection Classification mitigation for homeowner-insurance effects, and campus screening/acoustic standards. Town Talk reports Commissioner Joe McPherson requested explicit electricity and water language, and KALB reports the board agreed to circulate a red-lined revision before Nov. 19. Investment framing: KALB says Applied Digital and an unnamed tenant are each expected to invest $3.6 billion ($7.2 billion total), while Town Talk describes a $3.6 billion project expected to create more than 400 jobs.
Rapides Parish profile (seat: Alexandria) →Jefferson Davis Parish data-center regulation ordinance
Data-center regulation ordinance adopted unanimously Nov. 10, 2026 (per KLFY); official minutes not yet published
KLFY, published on WGNO, reports that on Tuesday, Nov. 10, 2026, the Jefferson Davis Parish Police Jury voted unanimously to adopt an ordinance establishing requirements and regulations for data centers. Jennings Daily News reported the meeting was moved from Wednesday, Nov. 11 (Veterans Day) to Tuesday, Nov. 10. The Nov. 10 agenda listed a public hearing and a roll-call adoption motion as items 7-8. The same agenda listed a separate battery energy storage ordinance as items 5-6; this record does not state the outcome of that BESS vote. Parish Administrator Ben Boudreaux said the data-center ordinance was modeled on the parish's solar-farm rules from about three years ago, requires a decommissioning bond, bars using aquifers such as the Chico Aquifer for continuous cooling, and requires developers to abate adverse grid effects. Parish officials said no data-center proposal is active in the parish. As of Nov. 11, 2026, official minutes for the Nov. 10 meeting are not yet published. This is a separate ordinance from the October 14 I-1 permitted-use amendment, whose adoption remains unconfirmed in published minutes. No ordinance number is reported.
Jefferson Davis Parish profile (seat: Jennings) →Jefferson Davis Parish I-1 data-center zoning amendment agenda
On October 14, 2026 voting agenda; adoption outcome not yet confirmed in published minutes
At the Jefferson Davis Parish Police Jury's October 7 and October 14, 2026 agendas, items 11-12 covered a public hearing plus a motion for roll-call adoption of an ordinance amending Chapter 21 (Zoning), Section 21-11.1(d)(4), to add battery storage facilities and data centers as permitted uses in the I-1 (Light Industrial) district. As of November 11, 2026, the agendas/minutes page still lists October 14 minutes as not available, so the adoption outcome remains unconfirmed. This I-1 permitted-use amendment is separate from the Nov. 10 data-center regulation ordinance reported by KLFY.
Jefferson Davis Parish profile (seat: Jennings) →Beauregard Parish data-center moratorium
Moratorium in place through end of 2026; lifts only after an ordinance is adopted (per American Press, Nov. 5, 2026)
An American Press report published Nov. 5, 2026, says a Beauregard Parish Police Jury workshop held Wednesday afternoon addressed a data-center moratorium already in place through the end of 2026 to allow officials time to establish regulations. Police Jury President Eddie Ware said there will be no data centers until the moratorium is lifted, and that the only way it will be lifted is if an ordinance is voted on and in effect. Parish legal counsel David Morgan said that if no ordinance is accepted by the end of the year, the moratorium would be continued into 2027. This report does not state when the moratorium was adopted.
Beauregard Parish profile (seat: DeRidder) →West Feliciana Parish Hut 8 River Bend Phase II site plan and rezoning
Phase II site-plan and rezoning requests deferred to Jan. 4, 2027 P&Z review after resubmission and public notice
The West Feliciana Planning and Zoning Commission's November 2, 2026 proposed agenda records two River Bend DC LLC requests deferred from the October 5 meeting to January 4, 2027, following resubmission and another round of public notice. Item 8a concerns rezoning near 11988 LA Hwy 10 W. Item 8b concerns the Phase II data-center halls site plan at 2949 and 2965 LA Hwy 964 W. January 4 is the Planning and Zoning Commission review date; any Parish Council decision would follow separately. The Advocate's November 3 report describes proximity concerns involving the Star Hill neighborhood and quotes Hut 8 senior director of public affairs Hailey Miller saying updated applications would be submitted in December 2026. That report describes original Phase II plans of about 180 acres and two buildings of about 568,000 square feet each. Phase I remains under construction.
West Feliciana Parish profile (seat: St. Francisville) →New Orleans CPC vote on data-center rules
5-2 CPC vote against staff proposal; Council action pending
On October 13, 2026, the City Planning Commission voted 5-2 against staff's proposed data-center zoning framework, recommended a six-month extension of the citywide ban that expires in January, and urged a 1,000-foot residential buffer if data centers are later allowed.
LouisianAI Oct. 17 feature article →Ascension Parish 90-day data-center moratorium order
Moratorium approved unanimously October 26, 2026; ordinance returns January 21, 2027; official minutes not yet published
At the rescheduled October 26, 2026 regular meeting in Gonzales, the Ascension Parish Council unanimously agreed to hold off adopting new high-impact development rules and instead imposed a roughly 90-day data-center moratorium. Business Report and WBRZ both report members plan to visit data centers and other parishes during that window. The Advocate reports the ordinance is scheduled to return January 21, 2027, about four days before the moratorium is set to expire. The Pelican Post (Oct. 28, 2026) identifies the tabled ordinance as DC-26.01, an amendment to the Ascension Parish Unified Land Development Code to add Section 17-2052 for High Impact Development Facilities.
Ascension Parish hub →St. Charles Parish Luling M1/M2 rezoning vote pulled before council meeting
Rezoning deferred; returns to Planning Commission Dec. 3, 2026; no data-center proposal filed
FOX 8 reports the St. Charles Parish Council removed a proposed zoning change from its October 26, 2026 agenda hours before the meeting. The request concerns nearly 1,000 acres of Esperanza Land, LLC farmland in Luling fronting River Road and extending back to Louisiana Highway 3127; parish officials said the item may have been insufficiently advertised and must return to the Planning Commission on December 3 before it can come back to the council. FOX 8 and Hoodline both report Parish President Matthew Jewell said the current action is only a rezoning request and that neither the parish nor Esperanza Land is in talks with any company about a data center or warehouse. Residents raised data-center and industrial-development concerns, and the same coverage notes St. Charles rejected an eight-month data-center moratorium in April 2026 and then adopted June 2026 data-center rules for M1/M2 districts (including a 300-foot buffer, 25-foot landscape buffer, 55 dB residential-line noise cap, and weekday generator-testing window of 7 a.m.-6 p.m.).
St. Charles Parish profile (seat: Hahnville) →Richland Parish Oppidan data-center sketch-plan recommendation
Preliminary sketch plan recommended October 5, 2026 (pending documents and engineer review); reported by local newspaper
Richland Parish Police Jury reporting says jurors approved recommendations on four preliminary sketch plans at the October 5, 2026 meeting, including a proposed Oppidan Data Center on Highway 583 north of Herring Road (25 acres), pending all required documents and parish-engineer questions. This is a preliminary sketch-plan recommendation, not a final plat, permit, or zoning approval.
Richland Parish data-center hub →Caddo Parish moratorium resolution vote
Resolution 53 failed 4-6 (2 absent)
Resolution 53 did not impose a moratorium; it would have asked the zoning commission to consider one in zoned C-3, C-4, I-1, and I-2 districts. The measure failed 4-6 with two absences on August 31, 2026.
Caddo Parish data-center hub →