Infrastructure tracker

Louisiana data center map and list.

Start here: the tracked buildout in one paragraph.

LouisianAI separates source-backed campus records, source-backed multi-campus programs, and visible watch rows. The core denominator below has a $65.6B+ disclosed-capex floor across 4 records; published site MW is counted only where a source discloses a number. Generation and grid-enabling projects remain in the LPSC docket trail, not the campus totals. Hut 8's up-to-$10B Phase I ceiling stays visible on its record but outside the statewide floor.

4 core records + 2 watch rows · $65.6B+ disclosed-capex floor · 5,760 MW published site power · edition 2026.10.17
Core capex
$65.6B+
Published site MW
5,760
Active builds
3 / 4
LPSC dockets
3 open / 5
Operators
4
Parishes
5
Chronology

Louisiana data center timeline.

Every event below is tied to a named public source or explicitly marked as a watch-row signal with no publishable document. Field-level before → after diffs appear only where the record documents a change. Chronology verified 2026-09-23. The same payload is available as JSON at /api/v1/timeline.

Reset

29 events · 11 with field-level diffs · grouped by month, oldest first

July 2024

1 event
July 1, 2024IncentiveStatewideConfidence A

Act 730 data-center sales/use tax rebate takes effect

Act 730 of the 2024 Regular Session amended La. R.S. 47:305.73 to give approved data centers a state and local sales and use tax rebate, effective July 1, 2024. Eligibility requires LED certification, a sworn attestation of at least $200M of new Louisiana capital investment between July 1, 2024 and July 1, 2029, and at least 50 new direct, permanent Louisiana jobs.

November 2024

1 event

December 2024

2 events
December 4, 2024AnnouncementMeta Hyperion AI Data CenterConfidence A

LED: Meta selects Northeast Louisiana for $10B AI data center

Louisiana Economic Development announced Meta's $10 billion AI-optimized data center in Richland Parish, with the project expected to use the Act 730 program and the Quality Jobs program.

  • capex: not in public record → $10B announced (LED)

January 2025

1 event
January 1, 2025IncentiveStatewideConfidence A

Act 11 converts the Act 730 rebate into an exemption

Act 11 of the 2024 Third Extraordinary Session converted the data-center sales and use tax rebate into an exemption for taxable periods beginning on and after January 1, 2025.

  • incentives.act730.mechanism: Annual rebate (Act 730, 2024 Regular Session) → Exemption for taxable periods beginning on/after 2025-01-01 (Act 11)

February 2025

1 event

May 2025

1 event
May 22, 2025AnnouncementHut 8 River Bend Data CenterConfidence C

LouisianAI begins tracking Hut 8 River Bend

The desk opened its River Bend record for the West Feliciana Parish campus, anchored to Hut 8's project page ahead of the state's formal December 2025 announcement.

August 2025

3 events

December 2025

1 event
December 17, 2025AnnouncementHut 8 River Bend Data CenterConfidence B

LED: Hut 8 selects Southeast Louisiana for up-to-$10B AI data center

Louisiana Economic Development announced Hut 8's River Bend AI data center. The figure is an upper-bound Phase I disclosure and is not added to the statewide disclosed-capex floor.

  • capex: not in public record → Up to $10B (upper bound, LED)

January 2026

2 events
January 22, 2026ConstructionDelta Forge 1Confidence B

Applied Digital breaks ground on Delta Forge 1

Applied Digital broke ground on Delta Forge 1 near Boyce, describing 430 MW of total utility power, up to 300 MW of critical IT load, and an initial-operations target of mid-2027.

  • status: Announced → Under construction
  • mw: not in public record → 430 MW utility design (up to 300 MW critical IT)

February 2026

2 events
February 23, 2026AnnouncementAmazon Data Centers in Caddo & BossierConfidence B

STACK announces Louisiana data-center developments for the Amazon program

STACK Infrastructure announced data-center developments supporting economic growth in Louisiana — the controlling primary source for the $12B multi-campus Amazon/STACK program record across Caddo and Bossier parishes.

  • capex: not in public record → $12B reported (multi-campus program)
February 24, 2026LPSC docketStatewideConfidence A

LPSC opens U-37853 (Waterford 6 / Westlake generation)

The Commission opened Entergy Louisiana's request to construct Waterford 6 Power Station and Westlake Power Station — part of the broader large-load generation stack, not a single-customer docket.

March 2026

2 events
March 26, 2026LPSC docketMeta Hyperion AI Data CenterConfidence A

LPSC opens U-37882 (Meta expansion / Project Evest)

The Commission opened Entergy Louisiana's certification proceeding for the Meta expansion (Evest LLC / Project Evest): seven additional gas combined-cycle plants totaling more than 5,200 MW, roughly 240 miles of 500 kV transmission, storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables.

April 2026

2 events
April 16, 2026AnnouncementVantage East BankConfidence D

LouisianAI opens Vantage East Bank watch row

The desk opened a rumour-grade watch row for a possible Vantage Data Centers site search on the East Bank, tracked from supplier RFPs only. No operator, permit, or utility confirmation exists in the public record.

No publishable source document — watch-row signal

May 2026

4 events
May 2026Announcementmonth precisionHut 8 River Bend Data CenterConfidence C

$16M West Feliciana parish water works announced for River Bend

The Hut 8 River Bend record notes a $16 million parish water-system commitment announced in May 2026, supporting the campus's river-adjacent cooling posture.

May 6, 2026LPSC docketStatewideConfidence A

LPSC opens X-37921 large-load guidelines repository

The Commission opened the informational repository docket for its Large Load Additions Non-Binding Guidelines — the framework used to evaluate expedited filings like U-37882. No interventions are accepted.

June 2026

2 events

July 2026

3 events
July 1, 2026IncentiveMeta Hyperion AI Data CenterConfidence B

LED statement: Act 730 exemption granted for current data-center projects

A secondary report quoting an LED statement said the data-center sales/use tax exemption had been granted for current projects. Meta's Hyperion campus was expected to use the Act 730 and Quality Jobs programs per LED's December 2024 announcement; the project also carries a Richland Parish PILOT.

  • incentives.act730.status: Expected to use (LED, December 2024) → Exemption granted (LED statement reported July 2026)
July 13, 2026AnnouncementMeta Hyperion AI Data CenterConfidence A

Meta confirms 5 GW / $50B+ Hyperion build-out

Meta confirmed a 5 GW build-out costing more than $50 billion for its Richland Parish campus — up from the original $10B framing in LED's December 2024 announcement. The U-37882 expansion package remains under LPSC review.

  • capex: $10B announced (LED, December 2024) → $50B+ lower bound (Meta, July 2026)
  • mw: not in public record → 5,000 MW (compute capacity, confirmed)

August 2026

1 event
August 18, 2026AnnouncementAmazon Data Centers in Caddo & BossierConfidence B

LED: Amazon grows NW Louisiana planned investment to $18B

Louisiana Economic Development announced Amazon's planned Northwest Louisiana investment growing to $18 billion with a new Shreveport campus. The tracker record still carries the $12B multi-campus figure pending source re-verification against this release.

  • capex: $12B reported (multi-campus program) → $18B planned incl. new Shreveport campus (LED)
Parish data-center pages