Evidence graph

Claim-level provenance, navigable

Every material fact on the tracker — capex, MW basis, utility, operator, status — resolves to the exact source behind it. Supporting, conflicting, and superseded evidence stay on the record; claims with no public-record evidence are listed as explicitly unknown. Verified September 23, 2026; next source review by December 22, 2026.

46 claims · 48 evidence nodes · 6 claims without public evidence

48 evidence nodes

ClaimFieldStatementRelationConfidenceSourcePublished
Amazon Data Centers in Caddo & BossiercapexMillionsAmazon's own Louisiana investment page corroborates the program without a separate dated figure.supportingBAmazonundated
Amazon Data Centers in Caddo & BossiercapexMillionsSTACK Infrastructure's announcement is the controlling source for the reported $12B multi-campus program capex.supportingASTACK Infrastructure2026-02-23
Amazon Data Centers in Caddo & BossieroperatorAmazon, with STACK Infrastructure, operates the Caddo & Bossier campus program.supportingBAmazonundated
Amazon Data Centers in Caddo & BossierstatusThe program is announced; the Bossier final plat is approved.supportingASTACK Infrastructure2026-02-23
Amazon Data Centers in Caddo & BossierutilityAEP names SWEPCO's role serving the announced data center development.supportingBAEPundated
Amazon Data Centers in Caddo & BossierutilitySWEPCO's own readiness page corroborates SWEPCO as the northwest Louisiana utility for large-load projects.supportingBSWEPCOundated
Delta Forge 1capexMillionsLouisiana Economic Development announced $3.6 billion of investment for the Applied Digital AI factory campus.supportingALouisiana Economic Development2026-05-26
Delta Forge 1mwApplied Digital reports 430 MW of total utility design, with up to 300 MW of critical IT load — two distinct bases from one source.supportingAApplied Digital2026-01-22
Delta Forge 1operatorApplied Digital is the operator of Delta Forge 1.supportingAApplied Digital2026-01-22
Delta Forge 1statusDelta Forge 1 broke ground in January 2026 with a mid-2027 initial-operations target.supportingAApplied Digital2026-01-22
Delta Forge 1statusLED's announcement corroborates the campus as secured and advancing.supportingALouisiana Economic Development2026-05-26
Delta Forge 1utilityCleco is the confirmed power provider for Delta Forge 1.supportingBApplied Digital2026-01-22
Hut 8 River Bend Data CentercapexMillionsLouisiana Economic Development announced the project as a $10 billion site; the desk records it as an upper bound ("Up to $10B"), never a capital floor.supportingALouisiana Economic Development2025-12-17
Hut 8 River Bend Data CentermwHut 8's River Bend project page is the basis for the 330 MW utility-capacity figure.supportingCHut 8undated
Hut 8 River Bend Data CenteroperatorHut 8 is the operator of the River Bend campus.supportingCHut 8undated
Hut 8 River Bend Data CenterstatusThe campus is under construction in Phase I buildout.supportingBLouisiana Economic Development2025-12-17
Hut 8 River Bend Data CenterutilityEntergy Louisiana is the serving utility for the River Bend site.supportingBLouisiana Economic Development2025-12-17
R-37905 — Private-use electrical networks for new large loadscustomerR-37905 concerns prospective large-load customers generally.supportingALouisiana Public Service Commission2026-04-24
R-37905 — Private-use electrical networks for new large loadsstatusR-37905 opened April 24, 2026 as a notice proceeding on private-use electrical networks for prospective large loads.supersededALouisiana Public Service Commission2026-04-24
R-37905 — Private-use electrical networks for new large loadsstatusThe July 31, 2026 staff notice posting the procedural schedule and first set of RFIs is the controlling status document for R-37905.supersedesALouisiana Public Service Commission2026-07-31
R-37905 — Private-use electrical networks for new large loadsutilityR-37905 is a Commission-level framework proceeding, not a utility filing.supportingALouisiana Public Service Commission2026-04-24
U-37425 — Meta Phase 1 / Laidley LLCcustomerThe customer of record in U-37425 is Laidley LLC / Meta Platforms.supportingALouisiana Public Service Commission2024-11-08
U-37425 — Meta Phase 1 / Laidley LLCstatusU-37425 opened November 4, 2024 as the Entergy Louisiana generation and transmission filing for a single North Louisiana customer project.supersededALouisiana Public Service Commission2024-11-08
U-37425 — Meta Phase 1 / Laidley LLCstatusThe August 29, 2025 order approving the settlement is the controlling status document for U-37425, replacing the open-filing state.supersedesALouisiana Public Service Commission2025-08-29
U-37425 — Meta Phase 1 / Laidley LLCutilityEntergy Louisiana is the utility party in U-37425.supportingALouisiana Public Service Commission2024-11-08
U-37853 — Waterford 6 / Westlake generationcustomerU-37853 is a system-resource / large-load-growth docket, not a single-customer Meta docket.supportingALouisiana Public Service Commission2026-02-27
U-37853 — Waterford 6 / Westlake generationstatusU-37853 is an open certification proceeding for Waterford 6 and Westlake generation; the tracker does not represent the pending request as a final certification decision.supportingALouisiana Public Service Commission2026-02-27
U-37853 — Waterford 6 / Westlake generationutilityEntergy Louisiana is the utility party in U-37853.supportingALouisiana Public Service Commission2026-02-27
U-37882 — Meta Phase 2 / Evest LLC / Project EvestcustomerThe customer of record in U-37882 is Evest LLC / Meta Platforms (Project Evest).supportingALouisiana Public Service Commission2026-03-27
U-37882 — Meta Phase 2 / Evest LLC / Project Evestmw.generationPackageEntergy describes the expansion package as more than 5,200 MW of additional gas combined-cycle generation plus transmission, storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables.supportingALouisiana Public Service Commission2026-05-14
U-37882 — Meta Phase 2 / Evest LLC / Project EveststatusU-37882 is an open certification proceeding; the May 14, 2026 procedural order sets Commission consideration for the December 16, 2026 Business and Executive Session.supportingALouisiana Public Service Commission2026-05-14
U-37882 — Meta Phase 2 / Evest LLC / Project EveststatusEntergy's announcement of the Meta expansion agreement frames the customer-savings terms behind the filing.supportingBEntergyundated
U-37882 — Meta Phase 2 / Evest LLC / Project EvestutilityEntergy Louisiana is the utility party in U-37882.supportingALouisiana Public Service Commission2026-03-27
X-37921 — Large-load non-binding guidelinescustomerThe guidelines apply to all large-load customers.supportingALouisiana Public Service Commission2026-05-08
X-37921 — Large-load non-binding guidelinesstatusThe X-37921 docket record corroborates the repository status.supportingALouisiana Public Service Commission2026-05-08
X-37921 — Large-load non-binding guidelinesstatusX-37921 is an informational repository docket for the large-load non-binding guidelines; the public-comment window closed June 19, 2026.supportingALouisiana Public Service Commission2026-05-22
X-37921 — Large-load non-binding guidelinesutilityX-37921 is a Commission-level repository, not a utility filing.supportingALouisiana Public Service Commission2026-05-08
Meta Hyperion AI Data CentercapexMillionsMeta's July 13, 2026 announcement is the controlling source for the $50B+ lower-bound capex figure.supportingAMeta2026-07-13
Meta Hyperion AI Data CentermwMeta announces 5 GW (5,000 MW) for Hyperion on a compute-capacity basis.conflictingAMeta2026-07-13
Meta Hyperion AI Data CentermwThe U-37882 expansion filing describes more than 5,200 MW of new generation on a utility-design basis — a different MW basis than Meta's campus compute figure, not the same number.conflictingALouisiana Public Service Commission2026-03-27
Meta Hyperion AI Data CenteroperatorMeta Platforms is the operator of the Hyperion campus.supportingAMeta2026-07-13
Meta Hyperion AI Data CenterstatusThe campus is under construction; the U-37882 expansion package remains under LPSC review.supportingAMeta2026-07-13
Meta Hyperion AI Data CenterutilityEntergy Louisiana is the utility of record; U-37425 approved the Phase 1 generation and transmission package serving the campus.supportingALouisiana Public Service Commission2024-11-08
STACK Bossier site contextcapexMillionsSTACK's program announcement does not separately disclose Bossier-site cost; the desk records site capex as not-disclosed rather than inferring a share of the $12B program.supportingBSTACK Infrastructure2026-02-23
STACK Bossier site contextmwNo public source separately discloses the Bossier site's MW; the desk keeps the figure unknown.supportingBSTACK Infrastructure2026-02-23
STACK Bossier site contextoperatorSTACK Infrastructure is the developer of the Bossier site.supportingASTACK Infrastructure2026-02-23
STACK Bossier site contextstatusThe site is a watch row: a potential subsite within Amazon/STACK's $12B multi-campus program, not an independently disclosed campus.supportingCSTACK Infrastructure2026-02-23
STACK Bossier site contextutilityThe Bossier site sits in SWEPCO's northwest Louisiana service territory alongside the Amazon/STACK cluster.supportingCSTACK Infrastructure2026-02-23
Explicitly unknown

Claims with no public-record evidence

These claims are on the record as unknown. The desk does not infer values from nearby infrastructure; each stays empty until a named source surfaces.