Evidence graph
Claim-level provenance, navigable
Every material fact on the tracker — capex, MW basis, utility, operator, status — resolves to the exact source behind it. Supporting, conflicting, and superseded evidence stay on the record; claims with no public-record evidence are listed as explicitly unknown. Verified October 27, 2026; next source review by November 27, 2026.
49 claims · 50 evidence nodes · 9 claims without public evidence
50 evidence nodes
| Claim | Field | Statement | Relation | Confidence | Source | Published |
|---|---|---|---|---|---|---|
| Amazon Data Centers in Caddo & Bossier | capexMillions | Amazon's community investment page corroborates the northwest Louisiana program without a separate dated figure. | supporting | B | Amazon | undated |
| Amazon Data Centers in Caddo & Bossier | capexMillions | Amazon's August 18, 2026 update corroborates the $18B planned investment and names the third Shreveport campus. | supporting | A | Amazon | 2026-08-18 |
| Amazon Data Centers in Caddo & Bossier | capexMillions | LED's August 18, 2026 release is the controlling source for the reported $18B planned investment, including a third campus at Resilient Technology Park. | supersedes | A | Louisiana Economic Development | 2026-08-18 |
| Amazon Data Centers in Caddo & Bossier | capexMillions | STACK Infrastructure's February 23, 2026 announcement was the original controlling source for the reported $12B multi-campus program capex. | superseded | A | STACK Infrastructure | 2026-02-23 |
| Amazon Data Centers in Caddo & Bossier | operator | Amazon, with STACK Infrastructure, operates the Caddo & Bossier campus program. | supporting | B | Amazon | undated |
| Amazon Data Centers in Caddo & Bossier | status | The program is announced; the Bossier final plat is approved. | supporting | A | STACK Infrastructure | 2026-02-23 |
| Amazon Data Centers in Caddo & Bossier | utility | AEP names SWEPCO's role serving the announced data center development. | supporting | B | AEP | undated |
| Amazon Data Centers in Caddo & Bossier | utility | SWEPCO's own readiness page corroborates SWEPCO as the northwest Louisiana utility for large-load projects. | supporting | B | SWEPCO | undated |
| Delta Forge 1 | capexMillions | Louisiana Economic Development announced $3.6 billion of investment for the Applied Digital AI factory campus. | supporting | A | Louisiana Economic Development | 2026-05-26 |
| Delta Forge 1 | mw | Applied Digital reports 430 MW of total utility design, with up to 300 MW of critical IT load — two distinct bases from one source. | supporting | A | Applied Digital | 2026-01-22 |
| Delta Forge 1 | operator | Applied Digital is the operator of Delta Forge 1. | supporting | A | Applied Digital | 2026-01-22 |
| Delta Forge 1 | status | Delta Forge 1 broke ground in January 2026 with a mid-2027 initial-operations target. | supporting | A | Applied Digital | 2026-01-22 |
| Delta Forge 1 | status | LED's announcement corroborates the campus as secured and advancing. | supporting | A | Louisiana Economic Development | 2026-05-26 |
| Delta Forge 1 | utility | Cleco is the confirmed power provider for Delta Forge 1. | supporting | B | Applied Digital | 2026-01-22 |
| Hut 8 River Bend Data Center | capexMillions | Louisiana Economic Development announced the project as a $10 billion site; the desk records it as an upper bound ("Up to $10B"), never a capital floor. | supporting | A | Louisiana Economic Development | 2025-12-17 |
| Hut 8 River Bend Data Center | mw | Hut 8's River Bend project page is the basis for the 330 MW utility-capacity figure. | supporting | C | Hut 8 | undated |
| Hut 8 River Bend Data Center | operator | Hut 8 is the operator of the River Bend campus. | supporting | C | Hut 8 | undated |
| Hut 8 River Bend Data Center | status | The campus is under construction in Phase I buildout. | supporting | B | Louisiana Economic Development | 2025-12-17 |
| Hut 8 River Bend Data Center | utility | Entergy Louisiana is the serving utility for the River Bend site. | supporting | B | Louisiana Economic Development | 2025-12-17 |
| R-37905 — Private-use electrical networks for new large loads | customer | R-37905 concerns prospective large-load customers generally. | supporting | A | Louisiana Public Service Commission | 2026-04-24 |
| R-37905 — Private-use electrical networks for new large loads | status | The July 31, 2026 staff notice posting the procedural schedule and first set of RFIs is the controlling status document for R-37905. | supersedes | A | Louisiana Public Service Commission | 2026-08-14 |
| R-37905 — Private-use electrical networks for new large loads | status | R-37905 opened April 24, 2026 as a notice proceeding on private-use electrical networks for prospective large loads. | superseded | A | Louisiana Public Service Commission | 2026-04-24 |
| R-37905 — Private-use electrical networks for new large loads | utility | R-37905 is a Commission-level framework proceeding, not a utility filing. | supporting | A | Louisiana Public Service Commission | 2026-04-24 |
| U-37425 — Laidley LLC | customer | The customer of record in U-37425 is Laidley LLC / Meta Platforms. | supporting | A | Louisiana Public Service Commission | 2024-11-08 |
| U-37425 — Laidley LLC | status | U-37425 opened November 4, 2024 as the Entergy Louisiana generation and transmission filing for a single North Louisiana customer project. | superseded | A | Louisiana Public Service Commission | 2024-11-08 |
| U-37425 — Laidley LLC | status | The August 29, 2025 order approving the settlement is the controlling status document for U-37425, replacing the open-filing state. | supersedes | A | Louisiana Public Service Commission | 2025-08-29 |
| U-37425 — Laidley LLC | utility | Entergy Louisiana is the utility party in U-37425. | supporting | A | Louisiana Public Service Commission | 2024-11-08 |
| U-37853 — Waterford 6 / Westlake generation | customer | U-37853 is a system-resource / large-load-growth docket, not a single-customer Meta docket. | supporting | A | Louisiana Public Service Commission | 2026-02-27 |
| U-37853 — Waterford 6 / Westlake generation | status | U-37853 is an open certification proceeding for Waterford 6 and Westlake generation; the tracker does not represent the pending request as a final certification decision. | supporting | A | Louisiana Public Service Commission | 2026-10-13 |
| U-37853 — Waterford 6 / Westlake generation | utility | Entergy Louisiana is the utility party in U-37853. | supporting | A | Louisiana Public Service Commission | 2026-02-27 |
| U-37882 — Evest LLC / Project Evest | customer | The customer of record in U-37882 is Evest LLC / Meta Platforms (Project Evest). | supporting | A | Louisiana Public Service Commission | 2026-03-27 |
| U-37882 — Evest LLC / Project Evest | mw.generationPackage | Entergy describes the expansion package as more than 5,200 MW of additional gas combined-cycle generation plus transmission, storage, nuclear uprates, and up to 2,500 MW of Meta-funded renewables. | supporting | A | Louisiana Public Service Commission | 2026-10-16 |
| U-37882 — Evest LLC / Project Evest | status | U-37882 is an open certification proceeding; the May 14, 2026 procedural order sets Commission consideration for the December 16, 2026 Business and Executive Session. | supporting | A | Louisiana Public Service Commission | 2026-10-16 |
| U-37882 — Evest LLC / Project Evest | status | Entergy's announcement of the Meta expansion agreement frames the customer-savings terms behind the filing. | supporting | B | Entergy | undated |
| U-37882 — Evest LLC / Project Evest | utility | Entergy Louisiana is the utility party in U-37882. | supporting | A | Louisiana Public Service Commission | 2026-03-27 |
| X-37921 — Large-load non-binding guidelines | customer | The guidelines apply to all large-load customers. | supporting | A | Louisiana Public Service Commission | 2026-05-08 |
| X-37921 — Large-load non-binding guidelines | status | The X-37921 docket record corroborates the repository status. | supporting | A | Louisiana Public Service Commission | 2026-05-08 |
| X-37921 — Large-load non-binding guidelines | status | X-37921 is an informational repository docket for the large-load non-binding guidelines; the public-comment window closed June 19, 2026. | supporting | A | Louisiana Public Service Commission | 2026-05-22 |
| X-37921 — Large-load non-binding guidelines | utility | X-37921 is a Commission-level repository, not a utility filing. | supporting | A | Louisiana Public Service Commission | 2026-05-08 |
| Meta Hyperion AI Data Center | capexMillions | Meta's July 13, 2026 announcement is the controlling source for the $50B+ lower-bound capex figure. | supporting | A | Meta | 2026-07-13 |
| Meta Hyperion AI Data Center | mw | Meta announces 5 GW (5,000 MW) for Hyperion on a compute-capacity basis. | conflicting | A | Meta | 2026-07-13 |
| Meta Hyperion AI Data Center | mw | The U-37882 expansion filing describes more than 5,200 MW of new generation on a utility-design basis — a different MW basis than Meta's campus compute figure, not the same number. | conflicting | A | Louisiana Public Service Commission | 2026-03-27 |
| Meta Hyperion AI Data Center | operator | Meta Platforms is the operator of the Hyperion campus. | supporting | A | Meta | 2026-07-13 |
| Meta Hyperion AI Data Center | status | The campus is under construction; the U-37882 expansion package remains under LPSC review. | supporting | A | Meta | 2026-07-13 |
| Meta Hyperion AI Data Center | utility | Entergy Louisiana is the utility of record; U-37425 approved the Phase 1 generation and transmission package serving the campus. | supporting | A | Louisiana Public Service Commission | 2024-11-08 |
| STACK Bossier site context | capexMillions | STACK's program announcement does not separately disclose Bossier-site cost; the desk records site capex as not-disclosed rather than inferring a share of the $18B program. | supporting | B | STACK Infrastructure | 2026-02-23 |
| STACK Bossier site context | mw | No public source separately discloses the Bossier site's MW; the desk keeps the figure unknown. | supporting | B | STACK Infrastructure | 2026-02-23 |
| STACK Bossier site context | operator | STACK Infrastructure is the developer of the Bossier site. | supporting | A | STACK Infrastructure | 2026-02-23 |
| STACK Bossier site context | status | The site is a watch row: a potential subsite within Amazon/STACK's $18B multi-campus program, not an independently disclosed campus. | supporting | C | STACK Infrastructure | 2026-02-23 |
| STACK Bossier site context | utility | The Bossier site sits in SWEPCO's northwest Louisiana service territory alongside the Amazon/STACK cluster. | supporting | C | STACK Infrastructure | 2026-02-23 |
Explicitly unknown
Claims with no public-record evidence
These claims are on the record as unknown. The desk does not infer values from nearby infrastructure; each stays empty until a named source surfaces.
- Amazon Data Centers in Caddo & BossiermwProgram MW is not publicly disclosed.
- Vantage East BankcapexMillionsCapex is not publicly disclosed; the rumour-grade record carries no source.
- Vantage East BankmwMW is not publicly disclosed; the rumour-grade record carries no source.
- Vantage East BankutilityEntergy LA service area only; unconfirmed.
- Vantage East BankoperatorVantage Data Centers is rumour-grade, tracked from supplier RFPs only.
- Vantage East BankstatusRumoured — site search; no public-record evidence.
- U-38035 — Cleco / Applied Digital service packagestatusOpen certification proceeding. Cleco's filing seeks approval of an electric service agreement, a capacity contract with Tenaska through May 31, 2037, and related generation and grid-connection support. On September 16, 2026, the Commission unanimously set consideration no later than the March 2027 Business and Executive Session, with an October 15 written order directing the ALJ to compile the record without recommendation and setting hearing dates for January 26-27, 2027.
- U-38035 — Cleco / Applied Digital service packageutilityUtility party: Cleco Power LLC.
- U-38035 — Cleco / Applied Digital service packagecustomerCustomer of record: Applied Digital.
Keep reading
From the evidence graph to policy and briefs
LPSC and public-record claims on this graph continue into the policy hub, the docket search, and the weekly briefs.