U-38035 — Cleco / Applied Digital service package
Open certification proceeding. Cleco's filing seeks approval of an electric service agreement, a capacity contract with Tenaska through May 31, 2037, and related generation and grid-connection support. On September 16, 2026, the Commission unanimously set consideration no later than the March 2027 Business and Executive Session, with an October 15 written order directing the ALJ to compile the record without recommendation and setting hearing dates for January 26-27, 2027.
0 evidence nodes · claim lpsc-u-38035.status
No public-record evidence currently supports this claim. The desk records the fact as explicitly unknown rather than inferring it from nearby infrastructure, adjacent dockets, or program-level figures.