● Diligence · Power & interconnection
The power record, basis by basis.
Cleco · Verified September 23, 2026
Load bases are modeled separately and are never summed, averaged, or normalized into a single MW figure. Any basis without a named public source is recorded as not-in-public-record rather than estimated. Every populated value carries its own source; every basis without one is held explicitly as not in public record.
Load bases — six separate figures, never one
Design capacity
430 MWConfirmed
Initial campus design — 430 MW of total utility power across two buildings (utility-design basis), with the ability to scale in 2028 and beyond · as of January 22, 2026
Applied Digital · 2026-01-22 ↗Critical IT
300 MWConfirmed
Up to 300 MW of critical IT load, delivered through two initial 150 MW facilities · as of January 22, 2026
Applied Digital · 2026-01-22 ↗Service & offtake agreements
Agreements
Not in public record
No named service, interconnection, or offtake agreement is in the reviewed public record for this project.
Queue position
Not in public record
Cleco is the serving utility of record; no public interconnection queue position has been disclosed for the campus.
Grid dependencies
Substations
Not in public record
No named substation dependency is in the public record for this project.
Transmission
Not in public record
No named transmission dependency is in the public record for this project.
Generation & storage
Not in public record
No dedicated generation or storage dependency is in the public record for this project.
Rate, tariff & curtailment
Rate / tariff posture
Not in public recordCleco is the confirmed serving utility per the desk record; no project-specific LPSC docket or tariff approval was identified in the reviewed public record.
Curtailment risk
Unknown
No interruptibility, curtailment, or demand-response terms for this load appear in the reviewed public record; the risk is not assessed rather than assumed low.
● Diligence · Water & environmental
The water record, field by field.
Verified September 23, 2026
Every field below carries its own source or is held explicitly as not in public record. Cooling designs, withdrawal sources, and volumes are never inferred from nearby plants, river adjacency, or typical hyperscale designs.
Cooling
Cooling method
Not in public record
Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.
No cooling design for Delta Forge 1 is filed in the public record; the desk water posture for the project is to-be-verified.
Withdrawal & discharge
Withdrawal source
Not in public record
Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.
Discharge destination
Not in public record
Monitored through LDEQ water-permit notices, Louisiana Department of Conservation and Energy groundwater records, parish water-board minutes, USACE New Orleans District, and operator disclosures.
Authorized volumes
Not in public record
No daily-gallon authorization is filed at project level. Monitored through LDEQ water-permit notices, Conservation and Energy groundwater records, and parish water-board minutes.
Permits & agreements
Water / wastewater permits
Water-board / supply agreements
Not in public record
No parish water-board or supply agreement is in the public record. Monitored through parish water-board minutes and police-jury agendas.
Risk & exposure
Water stress
Not in public record
No site-level water-stress assessment for the Rapides Parish campus is in the public record.
Flood & hurricane
Not in public record
No FEMA flood-zone determination or hurricane-exposure assessment for the site is in the public record. Monitored through parish floodplain and hazard-mitigation records.
Wetlands
Not in public record
No wetlands delineation or Section 404 record for the campus is in the public record.
Emissions / air
Not in public record
No project-level air permit for on-site generation or backup equipment is in the public record.
Waste streams
Not in public record
No solid or hazardous waste stream filing for the campus is in the public record.
Environmental review
Review status
No standalone environmental review filing located
Not in public recordDesk records note the Boyce-area site is already industrial; no consolidated environmental review document is in the public record.
● Diligence · Real estate & community impact
The local-impact record, field by field.
Verified September 23, 2026
Land deals, incentive terms, contractor awards, and community exposure each carry a named source or are held explicitly as not in the public record. Construction and operations jobs are never merged, and no dollar figure is estimated without a published record.
Land & assessed value
Land transactions
Applied DigitalReported
date not public · price not public · 672.52 ac · parcel ref not public
672.52 acres allotted in the company's application to the England Airpark Economic & Industrial Development District; about 300 acres are announced for two buildings with the remainder held for 'future use'. Documents were obtained by KALB via records request; no sale price is public.
KALB News Channel 5 · 2026-06-25 ↗
Assessed value
Not in the public record
Rapides Parish assessment figures are not published; the ad-valorem equivalent is set by the PILOT fee schedule instead.
Incentives & tax
Incentive terms
Rapides Parish / EEIDD PILOTReported
25-year term
Economic Development Financing Term Sheet obtained by KALB: a flat annual fee in lieu of standard taxes — $27.4M in year 1, stepping down to $19.4M by years 22–25 — plus $18M per year for three years to regional taxing bodies and community development.
KALB News Channel 5 · 2026-06-25 ↗Act 730 sales-tax exemption (La. R.S. 47:305.73)Confirmed
20-year term
LED (May 26, 2026): Applied Digital "qualified for Louisiana's state and local sales and use tax exemption" on qualifying data center equipment. The statutory agreement term is 20 years, renewable for 10.
Louisiana Economic Development · 2026-05-26 ↗
Taxable-value implications
Reported
The PILOT replaces ad-valorem exposure with a fixed, declining fee schedule ($27.4M in year 1 down to $19.4M by years 22–25), so parish revenue is decoupled from the assessed value of the $3.6B build.
Method: Qualitative: restates the term-sheet schedule reported by KALB from a records request. LouisianAI publishes no independent assessment math.
Construction & contractors
Construction packages
Delta Forge 1 — two buildings across four overlapping phasesReported
Under construction — broke ground January 2026; initial operations targeted for 2027
contractor not public · value not public
Construction plans reflect schematics for two to three additional 'future' buildings; contractor awards are not in the public record.
KALB News Channel 5 · 2026-06-25 ↗
Contractor awards
Not in the public record
No contractor award is in the public record for this project; awards are monitored through parish bid postings and operator announcements.
Jobs & workforce
Operations jobs
200Reported
The term sheet obligates creating and maintaining 200 full-time jobs within five years at wages at or above 150% of the statewide annual average; LED projects 418 total new jobs in the Central Region.
KALB News Channel 5 · 2026-06-25 ↗Workforce availability
Reported
The PILOT term sheet hard-codes 200 full-time positions at or above 150% of the statewide average wage; Louisiana Central facilitated the project and coordinated regional due-diligence review.
Partners: Louisiana Central (regional economic-development organization)
KALB News Channel 5 · 2026-06-25 ↗Community exposure
Lodging & housing pressure
Not in the public record
No public reporting quantifies lodging or housing pressure around the Boyce build.
Roads & public services
Reported
LDEQ issued a May 27, 2026 citation for failure to control particulate emissions after citizen complaints about construction dust; the company says a corrective product was applied and conditions improved.
KALB News Channel 5 · 2026-06-25 ↗Reported
Residents pressed officials on NDAs, emergency-generator noise, and outage priority at a June 23, 2026 town hall; Cleco states the project pays its full infrastructure cost with no expected residential rate increase.
KALB News Channel 5 · 2026-06-25 ↗
Local tax-base exposure
Reported
The term sheet front-loads parish revenue — $27.4M in year 1 plus $18M per year for three years to regional taxing bodies — but the fee declines over time, and final distribution of the $18M payments was unresolved as of KALB's reporting.
KALB News Channel 5 · 2026-06-25 ↗§ Economic impact calculator
Stress-test the assumptions.
Edit the inputs to compare an ad-valorem proxy against a PILOT discount, construction labor hours, and peak power demand relative to an editable parish consumption baseline.