Search the whole Louisiana AI desk.
Find projects, dossier claims, LPSC dockets, source documents, entities, briefs, glossary terms, change records, and public-record references — then narrow by kind, authority, parish, confidence, evidence state, phase, or date. Every filter combination is a shareable URL.
LPSC opens U-37425 (Entergy LA resources for Meta Phase 1)
The Commission opened the first Meta Hyperion power docket — Entergy Louisiana generation and transmission resources for service to a single North Louisiana customer project (Laidley LLC / Meta Platforms).
LED: Meta selects Northeast Louisiana for $10B AI data center
Louisiana Economic Development announced Meta's $10 billion AI-optimized data center in Richland Parish, with the project expected to use the Act 730 program and the Quality Jobs program.
LouisianAI begins tracking Meta Hyperion
The desk opened its Meta Hyperion record five days after the LED announcement, anchored to the state's December 4, 2024 release.
LPSC approves the U-37425 settlement
The Commission approved the Meta Phase 1 settlement at its August 20, 2025 Business and Executive Session, clearing the initial generation and transmission package for the Richland Parish campus.
U-37425 order document dated
The U-37425 order document was dated August 29, 2025 — the controlling primary record for the approved Meta Phase 1 power package.
LPSC opens U-37882 (Meta expansion / Project Evest)
The Commission opened Entergy Louisiana's certification proceeding for the Meta expansion (Evest LLC / Project Evest): seven additional gas combined-cycle plants totaling more than 5,200 MW, roughly 240 miles of 500 kV transmission, storage, nuclear uprates, …
U-37882 procedural order sets schedule toward December 16, 2026
The Commission's May 14, 2026 procedural order in U-37882 directs a schedule for Commission consideration at the December 16, 2026 Business and Executive Session. It is a scheduling step, not a certification decision.
Meta confirms 5 GW / $50B+ Hyperion build-out
Meta confirmed a 5 GW build-out costing more than $50 billion for its Richland Parish campus — up from the original $10B framing in LED's December 2024 announcement. The U-37882 expansion package remains under LPSC review.