LPSC opens U-37425 (Entergy LA resources for Meta Phase 1)
The Commission opened the first Meta Hyperion power docket — Entergy Louisiana generation and transmission resources for service to a single North Louisiana customer project (Laidley LLC / Meta Platforms).
LPSC approves the U-37425 settlement
The Commission approved the Meta Phase 1 settlement at its August 20, 2025 Business and Executive Session, clearing the initial generation and transmission package for the Richland Parish campus.
U-37425 order document dated
The U-37425 order document was dated August 29, 2025 — the controlling primary record for the approved Meta Phase 1 power package.
LPSC opens U-37882 (Meta expansion / Project Evest)
The Commission opened Entergy Louisiana's certification proceeding for the Meta expansion (Evest LLC / Project Evest): seven additional gas combined-cycle plants totaling more than 5,200 MW, roughly 240 miles of 500 kV transmission, storage, nuclear uprates, …
U-37882 procedural order sets schedule toward December 16, 2026
The Commission's May 14, 2026 procedural order in U-37882 directs a schedule for Commission consideration at the December 16, 2026 Business and Executive Session. It is a scheduling step, not a certification decision.