Applied Digital Pledges $4 Million to Boyce Near Delta Forge 1

The community benefit agreement supports local infrastructure as Meta's Richland Parish data center faces questions over power needs and regulatory disclosures.

October 18, 2026·LouisianAI Editorial·4 minPower

Every material claim links to the cited source. Treat uncertainty notes as part of the record. This is not an approval, a completed operating milestone, or a substitute for the underlying filing.

Applied Digital has reached a $4 million community benefit agreement with the Town of Boyce to fund improvements, infrastructure enhancements, and economic growth. The deal was announced October 14, 2026, and ties directly to the company's Delta Forge 1 AI Factory, a $3.6 billion data center project located across the street from the town. Applied Digital agrees to $4 million community benefit deal for Boyce The agreement marks a structured approach to ensuring nearby residents see tangible returns from large-scale development activity in the area. Local officials have emphasized that proximity to the project site creates both opportunities and responsibilities for the company involved. Discussions leading to the pact focused on practical needs such as road maintenance, utility upgrades, and workforce training programs that could benefit Boyce residents over multiple years.

Town of Boyce Mayor Kelvin McCoy stated that the agreement ensures the community closest to the project receives meaningful opportunities. Louisiana Central facilitated discussions to confirm long-term benefits for Boyce given its location and connectivity to the site. Applied Digital's Community Engagement Coordinator Gail Adams noted appreciation for the mayor's advocacy. Applied Digital agrees to $4 million community benefit deal for Boyce The mayor highlighted how the funding could address longstanding infrastructure gaps that smaller municipalities often struggle to resolve through local budgets alone. Facilitators from Louisiana Central worked to align the company's project timeline with community priorities, creating a framework that ties payments to specific milestones. Adams described the process as collaborative, noting that early engagement helped shape terms acceptable to both the town and the developer.

Power demands draw opposition for Meta project

Separate developments in Richland Parish involve Meta's data center under construction, which opponents describe as having absurd power needs. The facility is estimated to consume roughly 4,500 megawatts on a continual basis. This figure is approximately four times the single-day record of 1,160 megawatts set by Entergy New Orleans customers during peak heat in June 2022. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Critics have organized public demonstrations to express concerns about the broader effects on regional energy resources and environmental conditions. The scale of continuous demand has prompted questions about whether existing generation capacity can accommodate the load without additional facilities.

Members of the Take the Power Back campaign protested the scale of the project and related plans for new gas-fired power plants. Organizers cited strains on the energy grid, water supply, and air quality from additional generation. Entergy Louisiana responded that the 20-year agreement requires Meta to pay its full share of infrastructure costs without subsidization by other customers. The company also pointed to more than 1,500 jobs tied to the buildout. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Campaign participants argued that rapid expansion of data center capacity could accelerate the need for new generation sources, potentially affecting air quality and water availability in surrounding parishes. Entergy Louisiana has maintained that contractual safeguards prevent cost shifting, while also underscoring employment gains expected during construction and ongoing operations.

A similar report reiterated Entergy's position that concerns about ratepayer impacts are misguided and that the project aligns with state directives for data centers to cover their own costs. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The report examined contractual language in detail and concluded that dedicated cost-recovery mechanisms protect residential and commercial customers from bearing incremental expenses. State policy guidance on large-load customers was referenced as supporting the structure of the agreement.

PSC declines disclosure requirement

The Louisiana Public Service Commission recently voted down an administrative law judge's order that would have required Meta to disclose calculations behind its job projections and electricity needs for the Richland Parish project. Logan Burke, executive director of the Alliance for Affordable Energy, commented on the decision in a LaPolitics Q&A. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta The commission's action leaves the existing regulatory framework in place without additional reporting mandates at this stage. Burke discussed the implications for transparency and how future oversight might evolve depending on project performance and public input.

Why it matters for Louisiana

These agreements and regulatory steps illustrate how data center projects intersect with local communities and statewide energy planning. The Boyce arrangement provides direct funding mechanisms, while the Meta project highlights ongoing debates over power infrastructure and transparency in large-scale developments. Applied Digital agrees to $4 million community benefit deal for Boyce [kalb.com](https://www.kalb.com/2026/10/13/massive-power-needs-meta-data-center-richland-parish-are-absurd-opponents-say/‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta) Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Community benefit agreements like the one reached in Boyce represent one avenue for channeling project-related resources toward immediate municipal needs, including physical improvements and economic initiatives. At the same time, larger facilities such as the Meta development in Richland Parish bring forward questions about long-term energy supply, grid stability, and the balance between economic development goals and resource constraints. Regulatory decisions by the Public Service Commission shape the level of information available to the public and stakeholders regarding project assumptions. Together, these elements demonstrate the layered considerations that accompany major technology infrastructure investments across Louisiana parishes. Local governments, utilities, advocacy groups, and state regulators each play distinct roles in determining outcomes that affect residents, businesses, and the broader energy system. The interplay between voluntary local agreements and formal regulatory proceedings underscores the complexity of accommodating rapid growth in data center capacity while addressing community and infrastructure priorities. Continued attention to these dynamics will influence how future projects are structured and evaluated throughout the state.

Evidence Used

Subscribe to daily brief + feature emails

Choose the brief, feature, or weekly digest. Every email includes one-click unsubscribe and RSS links.

Email preferences

By submitting, you ask LouisianAI to use this information for this request as described in the Privacy Notice.

← All briefs