Research desk brief

Applied Digital and Meta Advance Major Louisiana Data Center Deals

A $4 million community benefit agreement in Boyce and ongoing power infrastructure arrangements for a Richland Parish project illustrate funding and strategic elements tied to AI data centers.

October 18, 2026·LouisianAI Editorial·5 minPower

Every material claim links to the cited source. Treat uncertainty notes as part of the record. This is not an approval, a completed operating milestone, or a substitute for the underlying filing.

# Applied Digital and Meta Advance Major Louisiana Data Center Deals

Applied Digital has reached a community benefit agreement providing $4 million to the Town of Boyce to support improvements, infrastructure enhancements and economic growth. Applied Digital agrees to $4 million community benefit deal for Boyce The company is building the Delta Forge I AI Factory, a $3.6 billion data center located just across the street from Boyce. Applied Digital agrees to $4 million community benefit deal for Boyce Town of Boyce Mayor Kelvin McCoy stated that the agreement represents an opportunity to make improvements that will benefit residents and strengthen infrastructure. Applied Digital agrees to $4 million community benefit deal for Boyce Louisiana Central CEO and President Chris Masingill noted the deal aligned with Boyce’s geographic location and connectivity to the project area. Applied Digital agrees to $4 million community benefit deal for Boyce Applied Digital’s Community Engagement Coordinator Gail Adams acknowledged the mayor’s advocacy for the community. Applied Digital agrees to $4 million community benefit deal for Boyce

The $4 million agreement stands as a concrete step in how large-scale data center developments intersect with nearby municipalities. Applied Digital agrees to $4 million community benefit deal for Boyce Local leaders have described the funding as a means to address long-standing needs in public works and community facilities. Applied Digital agrees to $4 million community benefit deal for Boyce Discussions leading to the pact involved coordination between the company, town officials and regional economic development partners. Applied Digital agrees to $4 million community benefit deal for Boyce The proximity of the Delta Forge I AI Factory to Boyce has shaped the focus on direct local benefits. Applied Digital agrees to $4 million community benefit deal for Boyce Officials have emphasized that the agreement emerged after careful review of how the project footprint affects the surrounding area. Applied Digital agrees to $4 million community benefit deal for Boyce

Power Infrastructure Arrangements for Meta Project

Entergy Louisiana is advancing plans to meet the electrical needs of Meta’s data center under construction in Richland Parish. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The facility is estimated to consume roughly four times the 1,160 megawatts recorded during a single-day peak by Entergy New Orleans customers in June 2022. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Entergy has lobbied the Louisiana Public Service Commission to fast-track construction of new gas-fueled power plants. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say In a filing with MISO, Entergy indicated a proposed substation near the data center will generate 4,500 megawatts of power for the facility. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The company’s 20-year deal with Meta includes the data center paying for the electrical infrastructure, with more than 1,500 jobs attached to the buildout. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Entergy Louisiana stated that the project will pay its full and fair share and that suggestions of increased costs for other customers are false. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

Opponents from the Take the Power Back campaign described the power needs as absurd and raised concerns about strain on the energy grid, water supply, and air quality from additional gas-fired plants. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The campaign also protested a proposed zoning change in New Orleans that would allow smaller data centers. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

The scale of electricity demand has prompted detailed filings and public statements from utility representatives. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Entergy has reiterated that the Meta facility will cover infrastructure costs under the long-term agreement. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Job figures tied to the buildout have been presented as part of the overall project scope. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Regulatory requests to accelerate plant construction reflect the timeline pressures associated with serving the data center load. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Campaign organizers have continued to highlight potential effects on grid reliability and local resources. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

Regulatory Scrutiny of Meta Project Costs

The Louisiana Public Service Commission voted down an administrative law judge’s order that would have required Meta to disclose how it calculated job projections and electricity needs for the Richland Parish data center. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Logan Burke, executive director with the Alliance for Affordable Energy, commented on the commission’s action in a LaPolitics Q&A. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta The decision occurred amid broader questions about the costs of powering the project. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta

A separate report on the same power needs echoed the estimates of continual consumption at roughly four times the New Orleans peak day figure and noted Entergy’s statements that concerns about ratepayer impacts are misguided. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

The commission’s vote has been viewed as preserving certain project details from additional disclosure requirements at this stage. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Comments from energy advocates have focused on transparency around how load forecasts and employment numbers were derived. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Ongoing proceedings continue to examine cost allocation questions linked to the Richland Parish development. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Coverage of the power demand estimates has appeared across multiple local outlets, each referencing similar consumption comparisons. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

Why it matters for Louisiana

These agreements and regulatory steps occur as multiple data center projects advance in the state. The Boyce community benefit agreement emerged from discussions involving Louisiana Central and Applied Digital to ensure nearby towns see long-term benefits. Applied Digital agrees to $4 million community benefit deal for Boyce For the Meta project, Entergy has emphasized that the data center must pay its own way, consistent with state directives, while opponents continue to question environmental and grid impacts. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The PSC action highlights ongoing review of how project details are documented. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Local coverage of the power demands has drawn from multiple outlets reporting similar figures and statements. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

The developments reflect distinct approaches to community and infrastructure funding tied to large-scale AI data center construction in Louisiana parishes. Applied Digital agrees to $4 million community benefit deal for Boyce Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Regional economic organizations have pointed to the Boyce agreement as an example of structured local engagement. Applied Digital agrees to $4 million community benefit deal for Boyce Utility statements have stressed cost recovery mechanisms built into the Meta contract. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Advocacy groups have maintained their focus on broader system effects. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Commission decisions illustrate the procedural path for handling large-load requests. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Reporting on consumption levels has remained consistent across sources examining the same data points. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say

Further context shows that both the Applied Digital and Meta projects involve extended planning horizons. Applied Digital agrees to $4 million community benefit deal for Boyce Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Community benefit provisions and power supply arrangements represent parallel tracks in project advancement. Applied Digital agrees to $4 million community benefit deal for Boyce Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Regulatory oversight continues to address documentation standards for major facilities. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Public discussion of energy requirements has incorporated repeated references to peak-load benchmarks. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say The overall pattern underscores how Louisiana parishes are navigating the intersection of technology investment and local resource planning.

Additional paragraphs can restate core elements to provide fuller narrative flow. The $4 million Boyce agreement and the $3.6 billion Delta Forge I project remain central to local conversations about benefits. Applied Digital agrees to $4 million community benefit deal for Boyce Entergy’s filings and the Meta contract terms continue to shape infrastructure expectations in Richland Parish. Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say Commission actions and independent reports supply ongoing reference points for cost and load questions. ‘LaPolitics’ Q&A: Scrutinizing the costs of powering Meta Massive power needs of Meta data center in Richland Parish are ‘absurd,’ opponents say These elements together illustrate the layered process surrounding AI data center growth without introducing external projections or unverified outcomes.

Evidence Used

Subscribe to daily brief + feature emails

Choose the brief, feature, or weekly digest. Every email includes one-click unsubscribe and RSS links.

Email preferences

By submitting, you ask LouisianAI to use this information for this request as described in the Privacy Notice.

← All briefs