Cameron Campus No. 2 — initial Title V and PSD air applications
- Event date
- October 15, 2026
- Responsible authority
- Louisiana Department of Environmental Quality
- Project
- Cameron Campus Data Center No. 2 application
- Parish
- —
- Category
- air-permit
- Verified / next review
- November 19, 2026 / December 19, 2026
View the Cameron Campus Data Center No. 2 application project profile.
No dependency links are recorded for this registry row.
Technical review, draft permits, public participation notices and final LDEQ decisions. The six records supplied under public-records request 109177 include the application, administrative completeness and expedited-processing documents. An issued final Title V or PSD permit remains unverified.
No expected date published
Louisiana Department of Environmental Quality · published October 19, 2026
PDF pages 1–3. LDEQ received the initial Title V and PSD applications on October 15, 2026 and found them administratively complete on October 19. Activities PER20260001 and PER20260002 remain subject to technical review. The October 21 expedited-processing approval letter (EDMS 15397512, PDF page 2) states that expedited processing does not guarantee permit issuance.