Hut 8 has selected Southeast Louisiana for a major artificial intelligence data center campus that could reach $10 billion in Phase I investment. The River Bend campus in West Feliciana Parish will initially draw 330 megawatts of utility capacity from Entergy Louisiana to support 245 megawatts of critical IT load for tenant Fluidstack. Construction is already underway, with operations targeted for the second quarter of 2027. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
The project is expected to create at least 75 direct jobs once Phase I is operational, plus an estimated 193 indirect positions according to Louisiana Economic Development. At peak construction the site could employ about 1,000 workers. Hut 8 plans to use state sales and use tax rebates for data center equipment and the Quality Jobs program. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
This commitment arrives as Louisiana regulators have streamlined approvals for new power plants serving large electricity users. In December 2025 the Public Service Commission adopted rules that shorten the review timeline for projects tied to data centers and similar loads, suspending competitive bidding in some cases while still requiring demonstration of lowest reasonable cost. The change was designed to replicate the expedited path used for Entergy’s turbines serving Meta’s Richland Parish facility. As data center rumors swirl, Livingston Parish President meets with battery storage company
Power demand questions have also surfaced in Livingston Parish, where NextEra Energy is exploring a 500-megawatt battery storage facility. Parish President Randy Delatte met with company representatives in October 2026 and noted that the project has filed with MISO. Permitting language references an unnamed commercial development, prompting speculation about a possible data center on a 690-acre industrial-zoned site off Buddy Ellis Road. No agreement has been finalized. Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic Development
Delatte has stated he believes a data center will arrive in the parish within five to ten years and has emphasized that any project must receive local approval without adverse resident impacts. Residents near the rezoned land have voiced concerns over water use, noise, and property values. The Livingston Parish Economic Development Council has clarified that the Buddy Ellis Road parcel is not among sites it is actively marketing for large industrial use. Louisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana Illuminator
Broader grid pressures add context. The International Energy Agency has warned that global data center electricity consumption could double to 1,000 terawatt-hours annually by 2030, with peak demand potentially rising 50 percent by 2035 in some regions. Limited transmission capacity and supply chain issues could delay projects. Livingston Parish President says data center is coming eventually
Hut 8’s agreement with Entergy for dedicated capacity illustrates one approach to meeting these needs while the new Public Service Commission rules aim to accelerate utility responses. The company’s choice of Louisiana follows other recent announcements, including Meta’s large-scale development in the northeast part of the state. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
The River Bend campus and related power infrastructure moves demonstrate how energy availability is becoming central to economic development decisions across Louisiana. Projects of this scale require coordinated planning between utilities, regulators, and local governments to balance growth with reliability and community considerations. Ongoing discussions in parishes such as Livingston show that site selection and permitting remain active processes even when specific tenants are not yet confirmed. Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic DevelopmentLouisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana IlluminatorAs data center rumors swirl, Livingston Parish President meets with battery storage companyRoundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
State officials have highlighted the role of incentive programs and workforce training in attracting these investments. As additional phases of the Hut 8 campus are evaluated, the experience gained from current approvals and grid studies will inform how Louisiana manages future demand from high-performance computing facilities. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
The regulatory adjustments adopted by the Public Service Commission in late 2025 reflect a broader effort to position Louisiana competitively for data center growth. By shortening review periods and adjusting bidding requirements for qualifying large-load projects, the commission seeks to align approval processes with the pace of private investment while maintaining cost safeguards. This framework builds directly on precedents established during earlier utility expansions for major technology tenants. As data center rumors swirl, Livingston Parish President meets with battery storage company
In West Feliciana Parish the Hut 8 development illustrates how dedicated utility capacity agreements can support rapid project timelines. The initial 330-megawatt draw from Entergy Louisiana is structured to serve the 245-megawatt IT load for Fluidstack, with construction already progressing toward the 2027 operational target. Economic development projections tied to the project include both direct employment and indirect roles supported by Louisiana Economic Development estimates. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
Livingston Parish continues to evaluate its own infrastructure proposals amid similar regional interest in large-scale energy assets. The 500-megawatt battery storage concept advanced by NextEra Energy remains in the exploratory stage following the October 2026 discussions with parish leadership. Local officials have stressed the necessity of community review and impact mitigation for any future development on the industrial-zoned acreage. Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic DevelopmentLouisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana Illuminator
Across the state these parallel efforts underscore the interplay between power planning, local permitting, and economic incentives. The International Energy Agency projections on rising global data center demand provide additional context for why Louisiana utilities and regulators are adapting processes to accommodate concentrated loads. Livingston Parish President says data center is coming eventually
Hut 8’s River Bend initiative, alongside the regulatory updates and ongoing parish-level conversations, shows how Louisiana is navigating the intersection of technology infrastructure and energy resources. Incentive structures such as tax rebates and workforce programs are expected to continue shaping site decisions as additional phases are considered. Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles
Evidence Used
- Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic Development — Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic Development
- As data center rumors swirl, Livingston Parish President meets with battery storage company Louisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana Illuminator — Louisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana Illuminator
- Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center - LED | Louisiana Economic Development As data center rumors swirl, Livingston Parish President meets with battery storage company — As data center rumors swirl, Livingston Parish President meets with battery storage company
- Louisiana creates fast track to approve power plants for data centers, big electricity users • Louisiana Illuminator Livingston Parish President says data center is coming eventually — Livingston Parish President says data center is coming eventually
- Livingston Parish President says data center is coming eventually Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles — Roundup: Louisiana Tech’s next leader / Grid under pressure / Homebuying hurdles